MIS17-00203
| ELE-Conference | 6/23/2017 | 6/23/2017 | 6/23/2017 3:22:25 PM | P | DEFR |
|
|
Defer to 375
|
MIS17-00204
| ELE-Conference | 6/23/2017 | 6/23/2017 | 6/23/2017 3:06:06 PM | P | FAIL |
|
|
Idaho Power complaint- NEC 230.24- Overhead service entrance conductors shall clear a flat to 3/12 pitch roof by 8' or 4/12 and steeper by 3' minimum. BCC 4-05-18 Any extension or addition of electrical requires an electrical permit. Heater being added to powder bath as noted on BLD15-04178 requires permit. '
Spoke with owner. Slow moving will pull electrical permit for new service for shop and sub-feed house. Overhead service conductor supported off roof by wood cross members.
|
ELE17-01292
| Final | 6/23/2017 | 6/23/2017 | 6/23/2017 2:31:42 PM | P | PASS |
|
|
Contact: Paul Wheeler Phone #: ###-#### Inspection requested via web by Deb Gooden Contractor seperated grounded and grounding at permenant service connection. Final ok
|
ELE17-01291
| Final | 6/23/2017 | 6/23/2017 | 6/23/2017 1:45:11 PM | P | PASS |
|
|
Contact: Paul Wheeler Phone #: ###-#### Inspection requested via web by Deb Gooden Contractor seperated grounded and grounding at permenant service connection. Final ok
|
ELE17-01286
| Final | 6/23/2017 | 6/23/2017 | 6/23/2017 1:44:48 PM | P | PASS |
|
|
Contact: Paul Wheeler Phone #: ###-#### Inspection requested via web by Deb Gooden Contractor seperated grounded and grounding at permenant service connection. Final ok
|
ELE17-01284
| Final | 6/23/2017 | 6/23/2017 | 6/23/2017 1:44:25 PM | P | PASS |
|
|
Contact: Paul Wheeler Phone #: ###-#### Inspection requested via web by Deb Gooden Contractor seperated grounded and grounding at permenant service connection. Final ok
|
ELE17-01285
| Final | 6/23/2017 | 6/23/2017 | 6/23/2017 1:44:02 PM | P | PASS |
|
|
Contact: Paul Wheeler Phone #: ###-#### Inspection requested via web by Deb Gooden Contractor seperated grounded and grounding at permenant service connection. Final ok
|
ELE17-01299
| Final | 6/23/2017 | 6/23/2017 | 6/23/2017 1:43:35 PM | P | PASS |
|
|
Contact: Paul Wheeler Phone #: ###-#### Inspection requested via web by Deb Gooden Contractor seperated grounded and grounding at permenant service connection. Final ok
|
ELE17-01297
| Final | 6/23/2017 | 6/23/2017 | 6/23/2017 1:43:14 PM | P | PASS |
|
|
Contact:Paul Wheeler Phone #: ###-#### Inspection requested via web by Deb Gooden Contractor seperated grounded and grounding at permenant service connection. Final ok
|
ELE17-01301
| Final | 6/23/2017 | 6/23/2017 | 6/23/2017 1:42:45 PM | P | PASS |
|
|
Contact: Paul Wheeler Phone #: ###-#### Inspection requested via web by Deb Gooden Contractor seperated grounded and grounding at permenant service connection. Final ok
|
ELE17-01289
| Final | 6/23/2017 | 6/23/2017 | 6/23/2017 1:42:18 PM | P | PASS |
|
|
Contact: Paul Wheeler Phone #: ###-#### Inspection requested via web by Deb Gooden Contractor seperated grounded and grounding at permenant service connection. Final ok
|
ELE17-01287
| Final | 6/23/2017 | 6/23/2017 | 6/23/2017 1:41:40 PM | P | PASS |
|
|
Contact: Paul Wheeler Phone #: ###-#### Inspection requested via web by Deb Gooden Contractor seperated grounded and grounding at permenant service connection. Final ok
|
ELE17-01288
| Final | 6/23/2017 | 6/23/2017 | 6/23/2017 1:40:38 PM | P | PASS |
|
|
Contact: Paul Wheeler Phone #: ###-#### Inspection requested via web by Deb Gooden Contractor seperated grounded and grounding at permenant service connection. Final ok
|
ELE17-01290
| Final | 6/23/2017 | 6/23/2017 | 6/23/2017 1:39:37 PM | P | PASS |
|
|
Contact: Paul Wheeler Phone #: ###-#### Inspection requested via web by Deb Gooden Contractor seperated grounded and grounding when permenant service connected. Final ok
|
ELE17-00852
| Electrical Rough-In | 6/23/2017 | 6/23/2017 | 6/23/2017 1:06:49 PM | A | PASS |
|
|
Call Chris for ceiling grid inspection on 2nd floor. Close to 10 AM please. Phone #: ###-#### Inspection requested via web by Rafael Castillo Discussed 410.62(C)(1)(b)- LED luminaires with flexible cords can terminate above grid if in a raceway and box is located not more than 6" above grid, pics to be taken. 1st floor storage room, 2nd floor- elevator lobby, stair lobby, rooms and areas 204, 205, 206, 207, 208, 221 storage rm grid rough in ok cover
|
ELE16-01946
| Final | 6/22/2017 | 6/23/2017 | 6/23/2017 11:45:58 AM | A | FAIL |
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton Test buttons on exterior FR. egress lighting. 3rd floor- All floors move disconnecting means with in 6'7" of floor for furnaces. 300.15- Open boxes shall have covers. old Sw in HVAC room. Exit box east stair. MEZZ- 210.8- GFCI receptacle with in 6' of janitors basin. Covers for gutter and recept in data room. Mech. terminate MC in a box. Center class room exit missing. 1st floor- add show window receptacles for 20' of window length. Check manufacturers instruction for heater mounted face down at ceilings. Dead receptacles and covers in server rm. Parking garage- Cover or remove old boxes in pillars where wir is present. Open ceilling box. Cover recept in mech under control. GFCI all garage receptacles.
|
ELE17-01964
| Electrical Rough-In | 6/22/2017 | 6/23/2017 | 6/23/2017 10:17:23 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Mark M Permit for the relocation of underground power for signs on south east corner of parking garage and hospital lots. Underground rough in ok cover
|
ELE17-01936
| Temporary Service | 6/22/2017 | 6/23/2017 | 6/23/2017 10:01:08 AM | A | PASS |
|
|
John Phone #: ###-#### load wiring not istalled at time of inspection. t/s u/g n ok
|
ELE17-01966
| Permanent Service | 6/22/2017 | 6/23/2017 | 6/23/2017 9:45:57 AM | A | PASS |
|
|
We are changing a service from overhead to underground. Would like to get an inspection as close to 10:00 as possible, so we can get their power back on. Thanks so much Phone #: ###-#### Inspection requested via web by Barbara Szurgot p/s u/g rec ok
|
ELE17-01979
| Electrical Rough-In | 6/22/2017 | 6/23/2017 | 6/23/2017 9:35:50 AM | A | PASS |
|
|
Listing inspection for PV modules and micro-inverters. Approved plans onsite, please call Ryan King with questions, ###-####. Thanks! Phone #: ###-#### Inspection requested via web by Ryan King At time of inspection array panels installed on roof with micro inverters under each panel. AC wiring yet to install to service. Listing confirmed on all equipment. Rough in ok
|
ELE17-01941
| Rough-In Permanent Service | 6/22/2017 | 6/23/2017 | 6/23/2017 8:43:16 AM | A | FAIL |
|
|
Phone #: ###-#### Inspection requested via web by Darryn Coburn 210.52- Up bed a receptacle outlet shall be installed with in 6' of door on back side of door. 300.4- NM cable shall be protected from physical damage where run thru hole that does not maintain 1 1/4" from framing surface. Back single garage outside corner, above WP on back of garage. 334.30- NM shall be secured with in 12" of box. Refer.
|