BLD95-01104
| INSP - Conference | 6/24/1997 | 6/24/1997 | 6/24/1997 12:00:00 AM | | PASS |
|
|
/ / 340 -
|
BLD95-01809
| INSP - Letter of compliance | 6/24/1997 | 6/24/1997 | 6/24/1997 12:00:00 AM | | PASS |
|
|
/ / 340 -
|
BLD95-01809
| INSP - Final | 6/24/1997 | 6/24/1997 | 6/24/1997 12:00:00 AM | | PASS |
|
|
/ / 340 -
|
BLD95-01809
| INSP - Letter of compliance | 6/24/1997 | 6/24/1997 | 6/24/1997 12:00:00 AM | | PASS |
|
|
/ / 340 -
|
BLD96-00040
| INSP - Conference | 6/24/1997 | 6/24/1997 | 6/24/1997 12:00:00 AM | | PASS |
|
|
/ / 340 -
|
BLD97-01667
| INSP - Letter of compliance | 6/24/1997 | 6/24/1997 | 6/24/1997 12:00:00 AM | | PASS |
|
|
/ / 340 - lc 12186
|
BLD97-01667
| INSP - Letter of compliance | 6/24/1997 | 6/24/1997 | 6/24/1997 12:00:00 AM | | PASS |
|
|
/ / 340 - lc 12186
|
BLD97-00494
| INSP - Foundation | 6/24/1997 | 6/24/1997 | 6/24/1997 12:00:00 AM | A | PART |
|
|
CHILLER FND; PENDING SPEC INSP REPORT
|
BLD97-01640
| INSP - Stop Work Order | 6/24/1997 | 6/24/1997 | 6/24/1997 12:00:00 AM | A | FAIL |
|
|
ISSUED SWO FOR SILANE STORAGE SHED/COVER AT WEST END CHEM STORAGE HP BLDG 6 PER GEORGE SLANE; CONSULTED W/ DAN STUART. PERMIT PENDING.
|
BLD97-00799
| INSP - Framing/Rough-in | 6/24/1997 | 6/24/1997 | 6/24/1997 12:00:00 AM | P | FAIL |
|
|
06/24/97 340 - cn, need engs ok for glu lam, truss attachment & break, f to ins
|
BLD97-01667
| INSP - Final | 6/24/1997 | 6/24/1997 | 6/24/1997 12:00:00 AM | P | PASS |
|
|
06/24/97 340 - ROOF FINAL done, appears ok
|
BLD96-02800
| INSP - Masonry | 6/24/1997 | 6/24/1997 | 6/24/1997 12:00:00 AM | P | PART |
|
|
06/24/97 340 - FYI:MASONRY GROUT & INTERIOR WALL - POURING AT 10:30 A.M. TODAY. SPECIAL INSPECTOR ON JOB.
|
BLD96-02800
| INSP - Footings | 6/23/1997 | 6/24/1997 | 6/24/1997 12:00:00 AM | P | PART |
|
|
06/24/97 340 - pend spec insp
|