BLD13-01688
| FIRE-Final Inspection | 6/23/2014 | 6/24/2014 | 6/24/2014 3:36:06 PM | P | PART |
|
|
life safety is complete in the Lab, Equipment Room and north half of the remodeled Lobby.
|
FIR14-00248
| INSP-Sprinkler Rough-in | 6/23/2014 | 6/24/2014 | 6/24/2014 2:51:21 PM | P | PASS |
|
|
24 hour air test passed. All piping can be covered. Rough-in passed for the front and rear canopies.
|
BLD13-03370
| FIRE-Final Inspection | 6/23/2014 | 6/24/2014 | 6/24/2014 2:50:18 PM | P | FAIL |
|
|
Provide additional smoke detector at the new exit into the mall corridor for the smoke evac system or have the mall engineer approve current setup. Need racking permit scheduled for inspection.
|
FIR14-00107
| INSP-Final Inspection | 6/23/2014 | 6/24/2014 | 6/24/2014 2:41:39 PM | P | PASS |
|
|
permit finaled
|
FIR14-00280
| INSP-Sprinkler Rough-in | 6/24/2014 | 6/24/2014 | 6/24/2014 1:23:50 PM | P | CANC |
|
|
Need the inspection latest as possible. partial Rough in for 2nd floor only. James is fitter onsite. if you cant get him call John at ###-#### Phone #: ###-#### >> Inspection requested via web by John Venche Inspection cancelled from web by: John Venche
|
BLD14-00402
| FIRE-Final Inspection | 6/23/2014 | 6/24/2014 | 6/24/2014 12:26:17 PM | A | PASS |
|
|
life safety passed. Signs have been posted
|
FIR13-00697
| INSP-Final Inspection | 6/23/2014 | 6/24/2014 | 6/24/2014 10:28:38 AM | A | PART |
|
|
Lab, Equipment Room and Lobby sprinkler work is complete.
|
FIR14-00279
| INSP-Alarm Testing | 6/23/2014 | 6/24/2014 | 6/24/2014 8:38:36 AM | A | DONE |
|
|
Lab, Equipment Room and Lobby fire alarm is complete.
|