Inspections for the day of: Friday, June 24, 2016.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Page
TitleFIRE INSPECTOR
Phone #208-914-5431
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR16-00261 INSP-Final Inspection6/22/20166/24/20166/24/2016 3:40:19 PMPPASS
Fire alarm inspection for level 1 passed/complete.
FIR16-00311 INSP-Sprinkler Rough-in/Hydro6/24/20166/24/20166/24/2016 2:28:21 PMPPASS
Rough to cover inspection for overhead fire sprinkler piping complete, overhead fire sprinkler approved for cover.
BLD16-02231 FIRE-Final Inspection6/24/20166/24/20166/24/2016 12:14:58 PMPPASS
No fire sprinkler modifications, no fire alarm modifications, fire extinguisher is in place and will tagged with current inspection tag. Final life fire safety inspection passed/complete.
BLD16-02244 FIRE-Final Inspection6/24/20166/24/20166/24/2016 11:55:58 AMPPASS
No fire sprinklers , no fire alarms, fire extinguisher is in place and will get an inspection tag. Final life fire safety inspection passed/complete.
BLD16-02232 FIRE-Final Inspection6/24/20166/24/20166/24/2016 11:41:31 AMPPASS
No fire sprinkler, no fire alarms, discussed location to mount fire extinguisher when painting is finished. Final life fire safety inspection passed/complete.
BLD16-02233 FIRE-Final Inspection6/24/20166/24/20166/24/2016 11:18:22 AMPFAIL
Fire sprinklers overspaced in front of showroom area, heads to close together in the rear storage area. Exit sign located by front entry needs to be serviced, exit light is currently inoperable.
FIR16-00404 INSP-Sprinkler Rough-in/Hydro6/24/20166/24/20166/24/2016 10:45:41 AMPPART
Rough to cover inspection for overhead fire sprinklers in the main entry hardlid, fire sprinkler piping above main entry hardlid approved for cover.
FIR16-00214 INSP-Final Inspection6/22/20166/24/20166/24/2016 10:26:26 AMAPASS
Final fire sprinkler inspection passed/complete.
FIR16-00146 INSP-Sprinkler Rough-in/Hydro6/23/20166/24/20166/24/2016 9:52:29 AMAPASS
Hydrostatic test for overhead fire sprinkler piping complete for level 5.
BLD16-01501 FIRE-Conference6/23/20166/24/20166/24/2016 9:32:39 AMADONE
Fire conference complete, discussed area's that would be acceptable to cover with ceiling tile.
BLD16-02291 FIRE-Final Inspection6/23/20166/24/20166/24/2016 9:07:48 AMAPASS
No fire sprinkler modifications, no fire alarm modifications, fire extinguishers are in place with current inspection tags. Final life fire safety inspection passed/complete.
FIR14-00870 INSP-Final Inspection6/21/20166/24/20166/24/2016 8:46:37 AMAPASS
Final fire alarm inspection passed/complete