FIR08-00256
| INSP-Sprinkler Rough-in/Hydro | 6/24/2008 | 6/25/2008 | 6/26/2008 10:06:14 AM | A | PART |
|
|
UG fire supply line hydrostatic testing completed.
|
FIR07-00672
| INSP-Final Inspection | 6/25/2008 | 6/25/2008 | 6/25/2008 4:25:30 PM | P | PART |
|
|
Tested all pull stations, tested all horns and strobes.KR
|
FIR04-00673
| INSP-Final Inspection | 6/25/2008 | 6/25/2008 | 6/25/2008 3:32:51 PM | P | PART |
|
|
Apt. units 812 and 812 1/2 smoke alarms tested okay.
|
FIR08-00256
| INSP-Supply line flush | 6/24/2008 | 6/25/2008 | 6/25/2008 3:23:34 PM | A | NR |
|
|
Need to coordinate inspection with United Water Co. as discussed.
|
FIR08-00423
| INSP-Final Inspection | 6/25/2008 | 6/25/2008 | 6/25/2008 3:22:42 PM | P | PASS |
|
|
Scope of fire sprinkler demo work completed, permit finaled.
|
FIR08-00370
| INSP-Sprinkler Rough-in/Hydro | 6/24/2008 | 6/25/2008 | 6/25/2008 3:21:31 PM | A | FAIL |
|
|
Need to add one upright head due to overspacing, missing hanger at one armover, FDC is obstructed by landscaping (GC agreed to remove plants as necessary), SW heads at dormers are okay, remainder of rough-in is acceptable.
|
FIR07-00309
| INSP-Sprinkler Rough-in/Hydro | 6/25/2008 | 6/25/2008 | 6/25/2008 1:22:42 PM | P | DONE |
|
|
Ok to cover, Sprinkler head moved per Troys notes. KR
|
BLD08-00080
| FIRE-Final Inspection | 6/24/2008 | 6/25/2008 | 6/25/2008 12:39:27 PM | P | NR |
|
|
Bill, please call 30 minutes prior; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
|
BLD07-03243
| BLD-Final | 6/25/2008 | 6/25/2008 | 6/25/2008 12:27:48 PM | P | CANC |
|
|
|
BLD07-03243
| FIRE-Final Inspection | 6/25/2008 | 6/25/2008 | 6/25/2008 12:21:06 PM | P | PASS |
|
|
Fire life safety complete. KR
|
FIR08-00432
| INSP-Final Inspection | 6/24/2008 | 6/25/2008 | 6/25/2008 12:18:25 PM | A | PASS |
|
|
Firen alarm issues resolved per plan notes.Duct smoke test complete. KR
|
FIR08-00327
| INSP-Sprinkler Rough-in | 6/25/2008 | 6/25/2008 | 6/25/2008 12:06:11 PM | P | PART |
|
|
Verified relocated pendent at the reception entry, tenting at the wet piping is acceptable, OH install is okay for cover at the sheetrock ceilings this TI only.
|
FIR08-00209
| INSP-Sprinkler Rough-in | 6/24/2008 | 6/25/2008 | 6/25/2008 11:40:45 AM | A | FAIL |
|
|
See stamped plan set for locations in need of adjustment including two overspaced pendent heads at the nurse station and three SSU's above the X-ray room which exceed min. spacing, also notified contractor to call in the shell FIR permit for rough-in inspection at next scheduled visit.
|
FIR08-00418
| INSP-Sprinkler Rough-in/Hydro | 6/24/2008 | 6/25/2008 | 6/25/2008 11:35:31 AM | A | PART |
|
|
C/N items repaired, OH fire sprinkler system modifications for the tenant area are approved for cover at the drop ceilings.
|
BLD07-01188
| FIRE-Final Inspection | 6/24/2008 | 6/25/2008 | 6/25/2008 11:33:36 AM | A | PASS |
|
|
Fire life safety inspection passed.
|
FIR08-00121
| INSP-Final Inspection | 6/24/2008 | 6/25/2008 | 6/25/2008 11:32:52 AM | A | PASS |
|
|
Remainder of items on the correction notice verified for compliance, final fire alarm inspection passed, permit finaled.
|
FIR08-00152
| FIR-Aging Inspection | 6/25/2008 | 6/25/2008 | 6/25/2008 9:22:46 AM | | DONE |
|
|
Work in progress, under construction.
|