ESC13-00567
| Site Preparation | 6/20/2013 | 6/20/2013 | | | |
|
|
|
ESC12-00147
| Site Final | 6/25/2013 | 6/25/2013 | 6/28/2013 3:30:43 PM | P | CANC |
|
|
I scheduled this to do at Bldg final. Didn't go out on Bldg final.
|
BLD13-00093
| BLD-Final | 6/24/2013 | 6/25/2013 | 6/25/2013 9:41:43 PM | P | CANC |
|
|
dave Phone #: ###-####
|
BLD11-02178
| BLD-Final | 6/24/2013 | 6/25/2013 | 6/25/2013 9:40:20 PM | P | CANC |
|
|
dave Phone #: ###-####
|
MIS13-00148
| BLD-Conference | 6/21/2013 | 6/25/2013 | 6/25/2013 2:58:00 PM | P | DONE |
|
|
Check back..... C/N issued. Make contact with City by July 10.
|
BLD13-01447
| BLD-Footing | 6/24/2013 | 6/25/2013 | 6/25/2013 2:21:50 PM | P | CANC |
|
|
Lucas Phone #: ###-####
|
ESC13-00028
| Site Final | 6/25/2013 | 6/25/2013 | 6/25/2013 2:19:24 PM | P | NR |
|
|
Paul phone
|
BLD13-00324
| BLD-Framing/Rough-in | 6/25/2013 | 6/25/2013 | 6/25/2013 2:17:13 PM | P | PASS |
|
|
Please call 1/2 prior Phone #: ###-#### >> Inspection requested via web by James Larkin
|
ESC13-00186
| Site Final | 6/25/2013 | 6/25/2013 | 6/25/2013 2:16:30 PM | P | CANC |
|
|
Ron phone
|
BLD13-01207
| BLD-Framing/Rough-in | 6/24/2013 | 6/25/2013 | 6/25/2013 1:05:42 PM | A | PASS |
|
|
tracy Phone #: ###-#### Final.....OK
|
BLD13-01207
| DOC - Permit Finaled | 6/25/2013 | 6/25/2013 | 6/25/2013 1:05:07 PM | P | PASS |
|
|
|
BLD13-00063
| BLD-Final | 6/22/2013 | 6/25/2013 | 6/25/2013 12:25:19 PM | A | PASS |
|
|
>> Inspection requested via web by Paul Thompson
|
BLD13-00063
| DOC - Permit Finaled | 6/25/2013 | 6/25/2013 | 6/25/2013 12:24:36 PM | P | PASS |
|
|
|
BLD13-00063
| DOC - Permit Finaled | 6/25/2013 | 6/25/2013 | 6/25/2013 12:20:07 PM | P | PASS |
|
|
|
BLD13-00985
| BLD-Framing/Rough-in | 6/24/2013 | 6/25/2013 | 6/25/2013 11:46:33 AM | A | PASS |
|
|
joe Phone #: ###-####
|
BLD13-01380
| BLD-Foundation | 6/24/2013 | 6/25/2013 | 6/25/2013 10:56:52 AM | A | PART |
|
|
mike Phone #: ###-#### All rebar in foundation and basement wall OK. Cannot determine South setback. No survey done. Contractor proceeding without verification of South property line.
|
BLD12-00688
| BLD-Footing | 6/24/2013 | 6/25/2013 | 6/25/2013 10:32:10 AM | A | PASS |
|
|
Inspect posts and approve for concrete in front of building 7 Phone #: ###-#### >> Inspection requested via web by Fred Depold
|
BLD13-01290
| BLD-Footing | 6/24/2013 | 6/25/2013 | 6/25/2013 10:30:45 AM | A | PASS |
|
|
Mike, building 14 footing/rebar inspection. Phone #: ###-#### >> Inspection requested via web by Mike McHargue Verbal From Bob Arnold Sub Grade OK.
|
BLD13-00318
| BLD-Energy code compliance | 6/25/2013 | 6/25/2013 | 6/25/2013 10:28:34 AM | A | PASS |
|
|
Please call 1/2 hr prior.
Thanks jim Phone #: ###-#### >> Inspection requested via web by James Larkin
|