FIR07-00087
| FIR-Aging Inspection | 6/26/2007 | 6/26/2007 | 6/27/2007 10:15:27 AM | | DONE |
|
|
Tenant work in progress.
|
FIR07-00205
| INSP-Sprinkler Rough-in | 6/25/2007 | 6/26/2007 | 6/26/2007 5:02:14 PM | P | FAIL |
|
|
Inspected OH rough-in for the 2nd level areas A and B sheets FP5 and 6, noted on plans defficient areas with missing heads, overspaced heads, hangers, retaining straps, areas not yet complete etc., flex heads in the cleanroom are not completed at this time.
|
FIR06-00940
| INSP-Sprinkler Rough-in | 6/25/2007 | 6/26/2007 | 6/26/2007 4:39:51 PM | P | PART |
|
|
Verified corrections have been made for the basement level piping, noted two stair enclosures are not yet piped, some upright heads in the corridor may become blocked due to excessive amounts of mechanical and electrical equipment in process of installation below the heads.
|
FIR07-00453
| INSP-Final Inspection | 6/22/2007 | 6/26/2007 | 6/26/2007 4:35:35 PM | P | NR |
|
|
Permit work is not completed for final at this time.
|
FIR07-00453
| INSP-Sprinkler Rough-in | 6/22/2007 | 6/26/2007 | 6/26/2007 4:34:42 PM | P | PART |
|
|
Some items noted at previous inspection including added heads in the lobby restroom, relocated heads at the 2nd floor conference room have been completed. Remaining items include missing heads at the cash and vault rooms, missing escutcheons, one head at the teller lobby to be replaced, covered heads at the 1st floor west stair landing, still need final for the shell and core permit.
|
FIR06-00615
| INSP-Sprinkler Rough-in/Hydro | 6/25/2007 | 6/26/2007 | 6/26/2007 1:36:30 PM | A | PASS |
|
|
Fire sprinkler system modifications passed inspection.
|
FIR07-00543
| INSP-Sprinkler Rough-in | 6/25/2007 | 6/26/2007 | 6/26/2007 12:13:19 PM | A | PART |
|
|
OH fire sprinkler modifications are approved for cover at the drop ceilings, final pending ceiling tile and escutcheons.
|
BLD06-03574
| FIRE-Final Inspection | 6/26/2007 | 6/26/2007 | 6/26/2007 11:46:03 AM | P | NR |
|
|
Building life safety final pending project related fire sprinkler permit final, one emergency light has been repaired.
|
FIR07-00311
| INSP-Final Inspection | 6/26/2007 | 6/26/2007 | 6/26/2007 11:44:16 AM | P | FAIL |
|
|
Previously noted pendent head in the storage room is still not correctly installed.
|
FIR07-00358
| INSP-Final Inspection | 6/26/2007 | 6/26/2007 | 6/26/2007 11:35:45 AM | P | PASS |
|
|
Fire alarm permit finaled.
|
BLD06-01651
| FIRE-Final Inspection | 6/26/2007 | 6/26/2007 | 6/26/2007 11:13:06 AM | P | PART |
|
|
Inspection for units 208, 209, 210, 211 on the west end of the building completed satisfactory, plastic cover and battery lid replaced on two SD while on site, noted the basement level storage areas will require smoke detectors and at least one fire extinguisher- see plan review notes and annotations, the remaining 8 units in this building are not yet completed for final.
|
BLD06-02542
| FIRE-Final Inspection | 6/25/2007 | 6/26/2007 | 6/26/2007 11:05:29 AM | A | NR |
|
|
Wrong project permit number called in, this building is not yet ready for final inspection, was intended for the adjacent structure.
|
FIR07-00358
| INSP-Alarm Testing | 6/25/2007 | 6/26/2007 | 6/26/2007 10:09:53 AM | A | PASS |
|
|
Corrections completed, fire alarm testing passed.
|