Inspections for the day of: Wednesday, June 26, 2013.
Number of inspections: 5
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD12-02722 FIRE-Final Inspection6/24/20136/26/20136/26/2013 3:38:25 PMPPASS
life safety passed
BLD13-01365 FIRE-Conference6/26/20136/26/20136/26/2013 3:13:33 PMPDONE
Monty wanted to know if I would approve a door stopper to hold open his rated doors. Apparently this door stopper releases when it hears a fire alarm audible signal. I deffered him to Scott Arellano for approval of the device.
BLD12-02415 FIRE-Conference6/25/20136/26/20136/26/2013 12:51:29 PMADONE
Bob Wheeler and I discussed what I would need a cover inspection on.
FIR13-00020 INSP-Sprinkler Rough-in6/25/20136/26/20136/26/2013 12:43:20 PMAPART
All piping can be covered except the piping above the vaulted ceiling. The tenting here is not complete.
FIR13-00273 INSP-Sprinkler Rough-in6/25/20136/26/20136/26/2013 12:37:27 PMAPART
The underground stub-out and the stub-in is ok to cover. No thrust blocking is being used since troy is gong to "rod" the IBR to the 90 elbows. This will need to be verified when the remaining underground is installed.