ESC14-00135
| General Inspection | 6/26/2015 | 6/26/2015 | 6/26/2015 3:55:51 PM | | PASS |
|
|
Construction complete. HIll slopes not yet vegetated or landscaped. Culdesac was cleaned. No ESC violations. Will monitor for stabilization.
|
ESC13-00684
| General Inspection | 6/26/2015 | 6/26/2015 | 6/26/2015 3:53:57 PM | | PASS |
|
|
|
ESC13-00755
| General Inspection | 6/26/2015 | 6/26/2015 | 6/26/2015 2:35:53 PM | | PASS |
|
|
Terraces is in good condition. No fugitive dust from vehicle traffic or construction. No discharges or trackout around perimeter. Materials are contained. No complaints received yet this summer from surrounding residents. Approved.
|
ESC14-00284
| General Inspection | 6/26/2015 | 6/26/2015 | 6/26/2015 2:25:28 PM | | PASS |
|
|
Home has has decorative rock ground cover and bushes. Bank along Draco and Windstary Way will keep the natural vegetation. Homewner will remove wattle. No sediment leaving site, no issues. No further ESC inspections needed at site, which is in vicinity of other projects by same builder.
|
ESC14-00284
| DOC - Permit Finaled | 6/26/2015 | 6/26/2015 | 6/26/2015 2:22:35 PM | P | PASS |
|
|
|
ESC15-00032
| Aging Inspection | 6/26/2015 | 6/26/2015 | 6/26/2015 2:06:22 PM | | PASS |
|
|
Home construction complete and yard is landscaped and stabiized. Backyard is already fenced in. Final site cleaning ongoing and no sediment or stockpiles.
ESC permit conditions satisfied. Approved.
|
ESC15-00032
| DOC - Permit Finaled | 6/26/2015 | 6/26/2015 | 6/26/2015 2:06:04 PM | P | PASS |
|
|
|
ESC14-00713
| General Inspection | 6/26/2015 | 6/26/2015 | 6/26/2015 1:43:37 PM | | PASS |
|
|
Permit sign clearly posted on security fence at entrance. Construction activity remaining confined to building footprint. No trackout to 10th or Grove Street. No fugitive dust or discharges observed. Still working on foundation.
|
ESC15-00710
| Conference | 6/26/2015 | 6/26/2015 | 6/26/2015 1:35:30 PM | P | PEND |
|
|
Advised TKO construction per building inspector's request on ESC controls. Flat infill lot in Northend. BMPs will mainly be housekeeping with frequent sweeping of sidewalk and gutter. Permit sign is now posted. Dust control will be need if vehicles are used around home.
|
ESC15-00178
| General Inspection | 6/26/2015 | 6/26/2015 | 6/26/2015 12:04:46 PM | P | PART |
|
|
Work already started early June. No site prep conducted. No violations at site, BMPs installed.
|
ESC15-00031
| Aging Inspection | 6/26/2015 | 6/26/2015 | 6/26/2015 11:25:53 AM | | PART |
|
|
WIP on storm drain and irrigation infrastructure. No SFH work yet at Fairmont Square. Some trackout within site but not to Bogart or Caswell. No fugitive dust observed.
Did not see permit sign or NOI information. Will check with contractor. Subdivision was built mostly prior to being annexed by Boise in late 2014.
|
ESC15-00029
| Aging Inspection | 6/26/2015 | 6/26/2015 | 6/26/2015 10:53:54 AM | | PASS |
|
|
Peppermill CBH SFH complete and landscaped. ESC permit conditions satisfied. Projects in subdivision currently in compliance.
|
ESC15-00029
| DOC - Permit Finaled | 6/26/2015 | 6/26/2015 | 6/26/2015 10:52:05 AM | P | PASS |
|
|
|
ESC15-00499
| BMP Violation | 6/26/2015 | 6/26/2015 | 6/26/2015 10:44:13 AM | A | PART |
|
|
-No permit sign posted. - No ESC site preparation scheduled.
Corrections: - post sign - schedule site prep inspection for monday. Site is inactive today - will need concrete washout
Note: Other BMPs including perimeter wattles are installed and there is no trackout or other violations occuring.
Notified RP of the violations and will meet Monday for site prep
|
ESC14-00200
| DOC - Permit Finaled | 6/26/2015 | 6/26/2015 | 6/26/2015 10:17:12 AM | P | PASS |
|
|
|
ESC14-00200
| General Inspection | 6/26/2015 | 6/26/2015 | 6/26/2015 10:17:05 AM | | PASS |
|
|
Data center grounds are contained by vegetated berm and all stormwater is treated & retained on site. Area to the west of the building is over 50% vegetated with grasses and weeds. No fugitive dust issues or observable erosion so determined to be low risk and revegetated in fall after temperatures lower.
All temporary BMPs removed. Business is in operation.
No further ESC inspection necessary. Permit finaled.
|
ESC14-00529
| Site Final | 6/26/2015 | 6/26/2015 | 6/26/2015 10:09:07 AM | P | PASS |
|
|
Construction has been complete for several months. Open areas have been vegetated/stabilized with sod, hydroseed, trees, and shrubs. Irrigation/drain channel lined with rip rap & river rock.
ESC permit conditions satisfied. All permits finaled.
|