BLD19-00323
| BLD-Aging Inspection | 6/26/2020 | 6/26/2020 | 6/30/2020 7:15:47 AM | | PEND |
|
|
|
MIS18-00110
| MIS-Aging Inspection | 6/26/2020 | 6/26/2020 | 6/30/2020 7:14:09 AM | | PEND |
|
|
permit is issued, no contact has been made for inspections
|
MIS19-00155
| MIS-Aging Inspection | 6/26/2020 | 6/26/2020 | 6/30/2020 7:12:24 AM | | PEND |
|
|
|
BLD19-02788
| BLD-Aging Inspection | 6/26/2020 | 6/26/2020 | 6/30/2020 7:11:45 AM | | PEND |
|
|
|
MIS19-00185
| MIS-Aging Inspection | 6/26/2020 | 6/26/2020 | 6/30/2020 7:10:05 AM | | CANC |
|
|
|
BLD20-00704
| BLD-Framing/Rough-in | 6/25/2020 | 6/26/2020 | 6/26/2020 4:23:10 PM | P | CANC |
|
|
Phone #: ###-#### Inspection requested via web by Kelly Stover
|
BLD18-04581
| BLD-Final | 6/25/2020 | 6/26/2020 | 6/26/2020 4:22:42 PM | A | PASS |
|
|
David Phone #: ###-####//corrections made//final complete//
|
BLD18-04581
| DOC - Permit Finaled | 6/26/2020 | 6/26/2020 | 6/26/2020 4:22:20 PM | P | PASS |
|
|
|
BLD18-04581
| BLD-Blower Door Test Results | 6/26/2020 | 6/26/2020 | 6/26/2020 4:22:10 PM | P | CANC |
|
|
2.88 ACH 50
|
BLD20-01283
| BLD-Wall Bracing | 6/25/2020 | 6/26/2020 | 6/26/2020 3:17:36 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle//add HD nails in pt//staples were peing added onsite as we walked shear//
|
BLD20-01286
| BLD-Wall Bracing | 6/25/2020 | 6/26/2020 | 6/26/2020 3:17:18 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle//add HD nails in pt//staples were peing added onsite as we walked shear//
|
BLD20-01287
| BLD-Wall Bracing | 6/25/2020 | 6/26/2020 | 6/26/2020 2:49:48 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle//add HD nails in pt//staples were peing added onsite as we walked shear//
|
BLD20-01289
| BLD-Wall Bracing | 6/25/2020 | 6/26/2020 | 6/26/2020 2:49:32 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle//add HD nails in pt//staples were peing added onsite as we walked shear//
|
BLD19-04651
| BLD-Conference | 6/26/2020 | 6/26/2020 | 6/26/2020 2:45:12 PM | P | DONE |
|
|
Screened // Mark Phone #: ###-####
|
BLD19-00535
| BLD-Energy code compliance | 6/26/2020 | 6/26/2020 | 6/26/2020 2:01:36 PM | P | PART |
|
|
INsulation inspection for 1st and 2nd floor approval for cover Phone #: ###-#### Inspection requested via web by Travis Blackburn//framing corrections made//stuff insulation around vent pipes//
|
BLD20-02040
| BLD-Final | 6/26/2020 | 6/26/2020 | 6/26/2020 1:30:32 PM | P | DONE |
|
|
fixed areas of missing water kick flashing Phone #: ###-#### Inspection requested via web by Kenneth Clark
|
BLD20-02040
| DOC - Permit Finaled | 6/26/2020 | 6/26/2020 | 6/26/2020 1:30:22 PM | P | PASS |
|
|
final complete, kick out flashings added at front entry area,, other areas of roof had a type of flashing already installed//
|
BLD19-04013
| BLD-Energy code compliance | 6/25/2020 | 6/26/2020 | 6/26/2020 11:28:45 AM | A | CANC |
|
|
Phone #: ###-#### Inspection requested via web by Matthew Bundy
|
BLD20-00344
| BLD-Framing/Rough-in | 6/25/2020 | 6/26/2020 | 6/26/2020 11:27:39 AM | A | PART |
|
|
screened // John Phone #: ###-####//areas marked on plans ok per plans and engineering clarification//some areas are pending ELE rough and were marked accordingly//
|
BLD20-01333
| BLD-Foundation | 6/25/2020 | 6/26/2020 | 6/26/2020 10:48:43 AM | A | PART |
|
|
The stem walls will be built first thing in the morning and should be available to be inspected by 8:30 or 9:00 am - Concrete is scheduled for Noon.
I am sorry the plans in the tube were not the city approved plans. I printed the wring file. They will be replaced as soon as i can get them re-printed. Thank you! Call Matt - ###-#### or Jeff - ###-#### Phone #: ###-#### Inspection requested via web by Matthew Swenson//city approved plans not onsite// small garage, rebar added to front wall per previous inspector//need to get approved plans onsite//WIP//
|
BLD20-01418
| BLD-Footing | 6/25/2020 | 6/26/2020 | 6/26/2020 10:36:15 AM | A | FAIL |
|
|
screened // francies Phone #: ###-####//CN issued//need side and back property lines marked nad pins located//provide city approved plans for inspections//
|
BLD20-00337
| BLD-Foundation | 6/25/2020 | 6/26/2020 | 6/26/2020 10:18:09 AM | A | PART |
|
|
screened // Chase Phone #: ###-####//part of Area C foundation walls//ok pend specials//maintain bar clearances//
|
BLD20-01152
| BLD-Framing/Rough-in | 6/25/2020 | 6/26/2020 | 6/26/2020 9:35:46 AM | A | PART |
|
|
Truss plans onsite. Call Alex at ###-#### with any questions. Phone #: ###-#### Inspection requested via web by Alex Macdonald//CN posted for bearing wall corrections at center truss bearing//need to install FP and have inspected//ok to insulate--DO NOT INSULATE AREA WHER FP IS UNTIL IT HAS BEEN INSPECTED//
|
BLD19-03050
| BLD-Foundation | 6/25/2020 | 6/26/2020 | 6/26/2020 9:05:16 AM | A | PART |
|
|
rebar // Dave ...... screened Phone #: ###-####//WIP//pend all special inspections//
|
BLD19-04398
| BLD-Framing/Rough-in | 6/25/2020 | 6/26/2020 | 6/26/2020 8:49:26 AM | A | PASS |
|
|
Please call before coming to make sure someone is home and give plenty of time to get home. Thanks Phone #: ###-#### Inspection requested via web by Shane Taylor//framing corrections made//energy ok//
|
BLD20-00680
| BLD-Wall Bracing | 6/25/2020 | 6/26/2020 | 6/25/2020 3:07:12 PM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Kelly Stover//ok when stud added and blocking added as discussed//
|