ESC11-00190
| General Inspection | 6/28/2011 | 6/28/2011 | 6/28/2011 4:00:17 PM | P | PASS |
|
|
|
BLD11-00687
| BLD-Conference | 6/28/2011 | 6/28/2011 | 6/28/2011 4:00:08 PM | P | DONE |
|
|
jason Phone #: ###-####
|
ESC11-00397
| BMP Violation | 6/28/2011 | 6/28/2011 | 6/28/2011 3:59:55 PM | P | PASS |
|
|
|
BLD11-01384
| BLD-Footing | 6/28/2011 | 6/28/2011 | 6/28/2011 3:59:42 PM | P | PART |
|
|
phil Phone #: ###-####
|
ESC10-00788
| General Inspection | 6/28/2011 | 6/28/2011 | 6/28/2011 2:46:33 PM | | PASS |
|
|
|
BLD11-01414
| BLD-Final | 6/28/2011 | 6/28/2011 | 6/28/2011 2:24:53 PM | P | PASS |
|
|
alissa Phone #: ###-####. ok for perm occ. once fire/life/safety signs perm.
|
BLD11-00781
| BLD-Concrete | 6/28/2011 | 6/28/2011 | 6/28/2011 2:12:56 PM | P | PASS |
|
|
Rebar mat for SOG Phone #: ###-#### >> Inspection requested via web by Chris Palmer
|
ESC11-00226
| Random Inspection | 6/28/2011 | 6/28/2011 | 6/28/2011 2:12:37 PM | P | PART |
|
|
Contractor needs to provide BMP measures around mortat mixing operations. Also discussed with contractor with his proceedures for mortar and grouting clean up after grout placements and end of day clean up.
|
BLD11-01162
| BLD-Framing/Rough-in | 6/27/2011 | 6/28/2011 | 6/28/2011 10:05:09 AM | A | PASS |
|
|
junior Phone #: ###-####. Interior steel stud walls, except at restroom.
|
BLD11-01362
| BLD-Framing/Rough-in | 6/27/2011 | 6/28/2011 | 6/28/2011 10:03:35 AM | A | PASS |
|
|
erin - as early as possible please Phone #: ###-####
|