BLD12-00476
| FIRE-Final Inspection | 6/27/2012 | 6/28/2012 | 6/28/2012 3:32:46 PM | P | PASS |
|
|
Fire life safety inspection passed. Door hardware at the office to be revised prior to structural final as discussed.
|
BLD11-02020
| FIRE-Final Inspection | 6/28/2012 | 6/28/2012 | 6/28/2012 3:31:15 PM | P | PART |
|
|
Final pending address numbers, missing tile at the computer room, signage at the door to the FACP, exit discharge light at the Myrtle street side, points map at the FACP.
|
FIR12-00292
| INSP-Final Inspection | 6/27/2012 | 6/28/2012 | 6/28/2012 3:28:38 PM | A | PASS |
|
|
Inspection passed. Fire alarm permit finaled.
|
FIR12-00317
| INSP-Final Inspection | 6/27/2012 | 6/28/2012 | 6/28/2012 3:27:08 PM | A | PASS |
|
|
Scope of fire sprinkler work passed both rough-in and final inspections. Contractor to seal opening at the DP in the cooler as discussed.
|
FIR11-00603
| INSP-Final Inspection | 6/25/2012 | 6/28/2012 | 6/28/2012 3:25:10 PM | A | PASS |
|
|
Completed fire alarm permit work acceptance test. Adjustments finished while on site.
|
FIR11-00587
| INSP-Alarm Testing | 6/28/2012 | 6/28/2012 | 6/28/2012 3:21:30 PM | A | PART |
|
|
Office phone #: ###-####
|
BLD11-02020
| FIRE-Final Inspection | 6/25/2012 | 6/28/2012 | 6/28/2012 12:00:00 AM | A | CANC |
|
|
As early as possible Phone #: 6314646 >> Inspection requested via mobile web by Gil
|