Inspections for the day of: Thursday, June 28, 2012.
Number of inspections: 14
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD12-00017 FIRE-Final Inspection6/28/20126/28/20126/29/2012 11:18:29 AMPPASS
life safety passed
BLD12-00818 FIRE-Final Inspection6/28/20126/28/20126/29/2012 11:16:47 AMPPASS
life safety passed
BLD12-01554 FIRE-Final Inspection6/28/20126/28/20126/28/2012 4:08:44 PMPCANC
Overbooked. Set back up for tomorrow morning.
FIR12-00319 INSP-Final Inspection6/27/20126/28/20126/28/2012 3:54:11 PMAFAIL
Life safety will be complete when the project related fire alarm permits are complete. Per the acting fire marshal, Gordon Goldsmith, the horns and the strobes need to meet NFPA 72 requirements for syncronization prior to a final sign off for the fire alarm permits.
FIR11-00435 INSP-Final Inspection6/27/20126/28/20126/28/2012 3:52:50 PMAFAIL
Per the acting fire marshal, Gordon Goldsmith, the horns and the strobes need to meet NFPA 72 requirements for syncronization prior to a final sign off for the fire alarm permits.
FIR12-00026 INSP-Final Inspection6/27/20126/28/20126/28/2012 3:52:26 PMAFAIL
Per the acting fire marshal, Gordon Goldsmith, the horns and the strobes need to meet NFPA 72 requirements for syncronization prior to a final sign off for the fire alarm permits.
BLD12-00345 FIRE-Final Inspection6/28/20126/28/20126/28/2012 3:40:34 PMPFAIL
The issues with the project related fire alarm permit, for phase I, needs to be addressed. Egress issues may be present for the exterior doors that currently utilize door magnets. Tom (building superintendant), Jim Storey and I are going to meet and discuss the issue and possible solutions.
FIR12-00151 INSP-Alarm Testing6/28/20126/28/20126/28/2012 3:30:13 PMPDONE
Todays inspection was to finish out phase I. The CRAC units were tested and functioned/shutdown correctly. The induct detectors are being used for hvac unit shutdown and fire/smoke damper operation. The induct detectors can not be used for hvac unit shutdown due to the air flow exceeding the listed range of the detector. The induct detectors can not be used for the damper operation because they do not meet the requirements of IMC 607.3.3.2. After a discussion it appears the VESDA system may provide a solution for both issues by meeting the "total area coverage" option of IMC section 606 and 607. Whatever the solution, it needs to be approved by Boise City Plan Review.
BLD11-01269 FIRE-Conference6/27/20126/28/20126/28/2012 3:15:00 PMADONE
Todays inspection was for fire life safety for 3rd and 4th floors of Tower 1 and Tower 2. Items needing completed are smoke alarm testing for tower 2 for both the third and fourth floors due to covers still being in place on the smoke alarms. Also there are still protective tape on several sprinkler heads. A smoke alarm in one bedroom of room 302 did not activate the other smoke alarms.
FIR11-00662 INSP-Alarm Testing6/28/20126/28/20126/28/2012 3:10:04 PMADONE
Todays inspection was for the 3rd and 4th for Towers 1 and 2. The third floor fire/smoke damper smoke detector needs to be replaced and re-tested. Also rooms at the fire wall separation on both the third and fourth floors did not operate due to work being completed on the other side of the fire wall. These circuits need to be complete before a sign off for the third and fourth floor areas.
FIR12-00274 INSP-Sprinkler Rough-in6/27/20126/28/20126/28/2012 11:24:36 AMAPART
Rough-in, for pendant sprinklers, for the most part is ok. Almost all of the upright sprinklers are blocked by hanging insulation. Also Mike and I found one location where upright heads are overspaced from an existing wall and some of the existing upright heads are blocked by duct work. These two items will need to be addressed prior to an approval for cover being given.
FIR12-00029 INSP-Final Inspection6/25/20126/28/20126/28/2012 9:42:16 AMAPASS
permit finaled
FIR12-00243 INSP-Final Inspection6/25/20126/28/20126/28/2012 9:41:38 AMAPASS
Permit finaled
FIR12-00242 INSP-Final Inspection6/25/20126/28/20126/28/2012 9:40:50 AMAPASS
Permit finaled