Inspections for the day of: Friday, June 28, 2013.
Number of inspections: 11
Percentage of inspections complete: 82 %
Percentage of inspections not complete: 18 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR13-00269 INSP-Sprinkler Rough-in6/28/20136/28/20137/5/2013 10:20:27 AMPDONE
Ok to cover 1 cooler-Don Phone #: ###-####
BLD12-00382 FIRE-Conference6/27/20136/28/20136/28/2013 3:40:55 PMADONE
Mike and I discussed the non-fire rated wood that has been installed in the parapet and options to allow it to remain.
FIR13-00087 INSP-Alarm Testing6/28/20136/28/20136/28/2013 3:13:49 PMPFAIL
No approved plans on site. No inspection performed. Also the sprinkler contractor was performing a hydro test.
FIR12-00670 INSP-Sprinkler Rough-in/Hydro6/27/20136/28/20136/28/2013 3:11:10 PMPPASS
Overhead hydro test passed.
FIR12-00648 FIR-Aging Inspection6/28/20136/28/20136/28/2013 12:02:12 PM DONE
work is in progress
BLD12-02334 FIRE-Final Inspection6/27/20136/28/20136/28/2013 10:29:11 AMAFAIL
Repair the exit sign over the main exit door, repair the emergency lighting at the north end of the lobby and provide testing for the three duct smoke detectors.
FIR12-00286 INSP-Final Inspection6/27/20136/28/20136/28/2013 10:21:52 AMAPASS
underground flush & forward flowtest passed. Permit finaled
FIR12-00518 INSP-Final Inspection6/27/20136/28/20136/28/2013 10:20:12 AMAPASS
Permit finaled
FIR13-00244 INSP-Final Inspection6/27/20136/28/20136/28/2013 10:18:35 AMAPASS
permit finaled
FIR13-00257 INSP-Sprinkler Rough-in/Hydro6/27/20136/28/2013 A 
7:AM requested. (discussed with Troy) Phone #: ###-#### >> Inspection requested via web by Jason Babien
BLD12-02063 FIRE-Final Inspection6/27/20136/28/2013 A 
Steve Phone #: ###-####