FIR13-00269
| INSP-Sprinkler Rough-in | 6/28/2013 | 6/28/2013 | 7/5/2013 10:20:27 AM | P | DONE |
|
|
Ok to cover 1 cooler-Don Phone #: ###-####
|
BLD12-00382
| FIRE-Conference | 6/27/2013 | 6/28/2013 | 6/28/2013 3:40:55 PM | A | DONE |
|
|
Mike and I discussed the non-fire rated wood that has been installed in the parapet and options to allow it to remain.
|
FIR13-00087
| INSP-Alarm Testing | 6/28/2013 | 6/28/2013 | 6/28/2013 3:13:49 PM | P | FAIL |
|
|
No approved plans on site. No inspection performed. Also the sprinkler contractor was performing a hydro test.
|
FIR12-00670
| INSP-Sprinkler Rough-in/Hydro | 6/27/2013 | 6/28/2013 | 6/28/2013 3:11:10 PM | P | PASS |
|
|
Overhead hydro test passed.
|
FIR12-00648
| FIR-Aging Inspection | 6/28/2013 | 6/28/2013 | 6/28/2013 12:02:12 PM | | DONE |
|
|
work is in progress
|
BLD12-02334
| FIRE-Final Inspection | 6/27/2013 | 6/28/2013 | 6/28/2013 10:29:11 AM | A | FAIL |
|
|
Repair the exit sign over the main exit door, repair the emergency lighting at the north end of the lobby and provide testing for the three duct smoke detectors.
|
FIR12-00286
| INSP-Final Inspection | 6/27/2013 | 6/28/2013 | 6/28/2013 10:21:52 AM | A | PASS |
|
|
underground flush & forward flowtest passed. Permit finaled
|
FIR12-00518
| INSP-Final Inspection | 6/27/2013 | 6/28/2013 | 6/28/2013 10:20:12 AM | A | PASS |
|
|
Permit finaled
|
FIR13-00244
| INSP-Final Inspection | 6/27/2013 | 6/28/2013 | 6/28/2013 10:18:35 AM | A | PASS |
|
|
permit finaled
|
FIR13-00257
| INSP-Sprinkler Rough-in/Hydro | 6/27/2013 | 6/28/2013 | | A | |
|
|
7:AM requested. (discussed with Troy) Phone #: ###-#### >> Inspection requested via web by Jason Babien
|
BLD12-02063
| FIRE-Final Inspection | 6/27/2013 | 6/28/2013 | | A | |
|
|
Steve Phone #: ###-####
|