Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR07-00497 INSP-Sprinkler Rough-in/Hydro6/29/20076/29/20076/29/2007 3:48:55 PMPPASS
See the city approved plans for the locations where the sprinkler piping can be covered. I also spoke with the building contractor about the fire blocking and sprinkler issues in the furred out walls.
BLD06-01095 FIRE-Final Inspection6/28/20076/29/20076/29/2007 1:21:02 PMAPASS
Life safety passed
BLD07-00025 FIRE-Final Inspection6/28/20076/29/20076/29/2007 1:17:29 PMAPASS
life safety passed
FIR07-00527 INSP-Sprinkler Rough-in6/28/20076/29/20076/29/2007 9:52:41 AMAPASS
Underground piping is ok to cover
FIR07-00429 INSP-Final Inspection6/28/20076/29/20076/29/2007 9:24:31 AMAFAIL
Upright heads are blocked by structural members, wrog heads have been installed and with the additional 90s added to the brachlines the minumum 5% cushion is not achieved. Larger piping is going to have to be installed.