FIR11-00025
| INSP-Final Inspection | 6/22/2011 | 6/22/2011 | | P | |
|
|
Troy phone #: ###-####
|
FIR11-00095
| INSP-Sprinkler Rough-in | 6/28/2011 | 6/29/2011 | 6/29/2011 4:51:31 PM | P | NR |
|
|
Partial walkthrough of the 1st floor office area only- noted field modifications at some areas in branchline routing, head location/type, relocated aux drain, etc., noted one missing head at a closet, missing hanger, heads, armovers and drops are not yet installed at some areas. Discussed elevator hoistway and SW head at the exterior canopy. Field mods will require as-built or plan modification depending on calcs.
|
BLD11-01241
| FIRE-Final Inspection | 6/29/2011 | 6/29/2011 | 6/29/2011 4:44:21 PM | P | PASS |
|
|
C/N items verified for completion. Life safety inspection passed.
|
FIR11-00293
| INSP-Sprinkler Rough-in | 6/29/2011 | 6/29/2011 | 6/29/2011 4:43:37 PM | P | PART |
|
|
OH work okay to cover, noted correction item finished.
|
BLD11-01389
| FIRE-Final Inspection | 6/29/2011 | 6/29/2011 | 6/29/2011 4:42:00 PM | P | PASS |
|
|
Corrections verified, life safety passed.
|
FIR11-00240
| INSP-Sprinkler Rough-in | 6/28/2011 | 6/29/2011 | 6/29/2011 4:41:01 PM | A | PART |
|
|
Overhead work approved for cover.
|
BLD11-00101
| FIRE-Conference | 6/28/2011 | 6/29/2011 | 6/29/2011 4:40:26 PM | A | DONE |
|
|
Regarding area of refuge notations per plan submital.
|
FIR11-00170
| INSP-Final Inspection | 6/28/2011 | 6/29/2011 | 6/29/2011 4:38:33 PM | A | PASS |
|
|
Fire sprinkler permit work passed final walkthrough.
|
FIR08-00239
| INSP-Sprinkler Rough-in | 6/28/2011 | 6/29/2011 | 6/29/2011 4:37:44 PM | A | PART |
|
|
See plans for areas on 1st thru 4th floors building #3 inspected today for cover approval. Noted locations in need of adjustment.
|
FIR11-00306
| INSP-Final Inspection | 6/28/2011 | 6/29/2011 | 6/29/2011 4:33:18 PM | A | PASS |
|
|
Hood suppression system operated correctly under test conditions. Inspection passed.
|