BLD15-00431
| FIRE-Final Inspection | 6/26/2015 | 6/29/2015 | 6/29/2015 2:40:35 PM | P | PASS |
|
|
Life fire safety inspection passed/complete
|
FIR15-00406
| INSP-Final Inspection | 6/29/2015 | 6/29/2015 | 6/29/2015 1:58:33 PM | P | PASS |
|
|
Sprinkler inspection passed/complete
|
FIR15-00112
| INSP-Final Inspection | 6/26/2015 | 6/29/2015 | 6/29/2015 10:04:14 AM | A | PART |
|
|
Notated areas in red ink on city approved drawings that are approved for final, some areas in mechanical room still needs piping/heads installed. Second floor sprinkler system needs 3 repairs, head located in elevator lobby is to close to heater register, needs to be upgraded to a 200 degree head. Both latrines in elevator lobby have heads that are painted, heads need to be replaced.
|