Inspections for the day of: Wednesday, June 3, 2009.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorSteven Webb
Title 
Phone #794-9491
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC09-00211 Complaint Inspection6/3/20096/3/20096/3/2009 2:57:48 PMPFAIL
Complaint from ACHD regarding trackout, verbal correction to RP to install better working trackout controls and to have workers park offsite whenever possible.
ESC09-00211 Tracking Control6/3/20096/3/20096/3/2009 2:56:12 PMPFAIL
Needs better controls inside the fence to reduce trackout. Verbal to RP
ESC08-00457 Random Inspection6/3/20096/3/20096/3/2009 2:54:10 PMPFAIL
Verbal to RP: Concrete washout is overflowing, needs sweeping of trackout along Nez Pierce. Complete by the end of the day of 6/8/09. Will follow up.
ESC08-00211 Random Inspection6/3/20096/3/20096/3/2009 2:47:29 PMPPASS
ESC08-00575 Site Final6/3/20096/3/20096/3/2009 2:01:41 PMAPART
Reviewed status of project with Hopkins Financial regarding requirement of ESC. Site has fairly consistent top growth of coverage but BMPs and dirt in gutter pan exists at misc. areas. Not ready to final.
ESC09-00286 Conference6/1/20096/3/20096/3/2009 1:58:27 PMADONE
9:00am Meet with Ground FX and Knife River over the implimenting the ESC/SWPPP plan. Met with Knife River, Dave Powell, (RiverRidge), Ground FX for erosion control discussion regarding upcoming project.
ESC06-00030 Random Inspection6/3/20096/3/20096/3/2009 1:58:24 PMPPART