BLD13-00166
| FIRE-Final Inspection | 6/3/2016 | 6/3/2016 | 6/3/2016 1:26:33 PM | P | FAIL |
|
|
The exit sign has not been repaired, an emergency light in the new area is non-functional and the new door hardware is still not single action. The fire extinguisher is current with its inspection but will expire next month.
|
BLD16-00065
| FIRE-Final Inspection | 6/3/2016 | 6/3/2016 | 6/3/2016 1:10:22 PM | P | FAIL |
|
|
Mount the fire extinguisher as discussed, provide exit sign as shown on the city approved plans or get plan review approval to delete, provide ADA hardware (single action) on the double store front doors or get plan review approval to remain as-is or to delete hardware entirely.
|
FIR16-00282
| INSP-Sprinkler Rough-in/Hydro | 6/2/2016 | 6/3/2016 | 6/3/2016 12:56:20 PM | P | PART |
|
|
1st floor hydro test passed. 2nd and 3rd failed due to visible loss of pressure at the guage.
|
FIR15-00709
| INSP-Sprinkler Rough-in | 6/3/2016 | 6/3/2016 | 6/3/2016 12:54:48 PM | P | PART |
|
|
2nd floor rough to cover inspection for the hardlids in the corridor passed except for the very west end in front of the stairs where a pendant head is missing.
|
FIR15-00822
| INSP-Final Inspection | 6/2/2016 | 6/3/2016 | 6/3/2016 12:15:45 PM | A | CANC |
|
|
Shilo has provided info on corrected gpm requirements that will need to be approved by Tim Frost for the forward flush
|
BLD15-01869
| FIRE-Final Inspection | 6/2/2016 | 6/3/2016 | 6/3/2016 11:07:27 AM | A | PART |
|
|
Temp 30 day Final - Quinton Phone #: ###-####
|
FIR16-00282
| INSP-Sprinkler Rough-in | 6/2/2016 | 6/3/2016 | 6/3/2016 10:32:02 AM | A | PASS |
|
|
Second floor piping is now ok to cover. Third floor piping can not be covered since the tenting inspection failed again. Riser room can not be covered until tenting is addressed
|
BLD16-01063
| FIRE-Final Inspection | 6/3/2016 | 6/3/2016 | 6/3/2016 9:50:06 AM | P | PASS |
|
|
life safety passed
|
FIR16-00347
| INSP-Final Inspection | 6/2/2016 | 6/3/2016 | 6/3/2016 9:49:17 AM | A | PASS |
|
|
Permit finaled
|