Inspections for the day of: Friday, June 30, 2006.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR06-00159 INSP-Final Inspection6/29/20066/30/20066/30/2006 4:27:39 PMAFAIL
One duct detector at first floor north plan FP2 failed to function, shunt trip for the elevator failed to operate, method to test the HD in the elevator control room not provided, need to remove cover at the sd above nac panel northeast side, security door is still not installed at the main entry exit.
FIR06-00128 INSP-Final Inspection6/30/20066/30/20066/30/2006 4:21:30 PMPPASS
Final fire sprinkler inspection passed, required corrections have been made, permit finaled.
BLD06-01235 FIRE-Final Inspection6/30/20066/30/20066/30/2006 2:30:31 PMPNR
The project related fire alarm permit must be requested for inspection and final prior to life safety final approval.
FIR06-00444 INSP-Sprinkler Rough-in6/30/20066/30/20066/30/2006 2:28:30 PMPPART
UG supply line and riser stub are good for cover, need to provide method for seismic clearance at the ductile riser where pipe will pass through floor slab.
FIR05-00713 INSP-Final Inspection6/29/20066/30/20066/30/2006 1:54:07 PMPFAIL
Several items need correction, project is not ready for final inspection at this time. Preliminary rough-in inspection completed today addressing items such as incorrect hangers, spacing, head temps, seismic bracing and clearance, riser and plans which do not match installation- See 10 item correction notice left on site for review of a partial list of defficiencies. C/N does not constitute a complete listing of all issues regarding fire sprinklers at this time.
FIR06-00250 INSP-Final Inspection6/28/20066/30/20066/30/2006 12:07:22 PMAPASS
Fire alarm work passed field inspection, permit finaled.
FIR06-00293 INSP-Final Inspection6/27/20066/30/20066/30/2006 12:06:37 PMAPASS
Fire sprinkler permit passed final inspection.
FIR05-00883 INSP-Supply line flush6/29/20066/30/20066/30/2006 11:27:05 AMAPART
UG supply line flush performed satisfactory.
FIR05-00425 INSP-Sprinkler Rough-in/Hydro6/29/20066/30/20066/30/2006 9:33:19 AMAPART
OH rough-in for the 11th floor is acceptable for cover at the hard lid areas.
FIR06-00444 INSP-Sprinkler Rough-in6/29/20066/30/20066/30/2006 12:00:00 AMACANC
Please call 1 hour prior to inspection. UG to cover.; Phone #: ###-#### Internet Inspection Request from: Trent Bice