Inspections for the day of: Wednesday, June 30, 2010.
Number of inspections: 6
Percentage of inspections complete: 83 %
Percentage of inspections not complete: 17 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD10-01103 FIRE-Conference6/28/20106/28/2010 P 
Jim Phone #: ###-#### or Mike ###-####
FIR10-00089 INSP-Sprinkler Rough-in6/30/20106/30/20106/30/2010 5:10:02 PMPFAIL
Missing one lateral seismic brace at the south end of the dry system main, shadowing at one office area, welded 2" outlets on the dry system mains serving branchlines at the exterior canopy at some locations are not properly graded, noted one dry pendent at the main entry has been added. See stamped plans for annotations.
FIR10-00205 INSP-Final Inspection6/30/20106/30/20106/30/2010 5:03:11 PMPPASS
Fire alarm work passed field testing, permit final approved.
BLD10-00664 FIRE-Final Inspection6/29/20106/30/20106/30/2010 5:02:10 PMANR
Work in progress, construction and finishes underway.
FIR10-00209 INSP-Alarm Testing6/29/20106/30/20106/30/2010 5:00:39 PMAPART
Completed notification appliance testing only for the remodel area. Duct detectors are not yet installed.
FIR10-00089 INSP-Sprinkler Rough-in/Hydro6/29/20106/30/20106/30/2010 4:58:31 PMAPART
Overhead hydrostatic test for both the wet and dry systems completed satisfactory.