FIR14-00430
| INSP-Sprinkler Rough-in | 6/29/2015 | 6/30/2015 | 6/30/2015 4:17:54 PM | P | PASS |
|
|
Hydrostatic test of two Dry Pipe systems protecting the grade level parking garage - 200 psi @ 2 hours - PASSED
|
FIR14-00531
| INSP-Sprinkler Rough-in/Hydro | 6/30/2015 | 6/30/2015 | 6/30/2015 4:17:39 PM | P | PASS |
|
|
Hydrotests of floors 2 and 4 - 200 psi @ 2hrs, - PASSED. NOTE: Floor 3 had a leak and floor 5 is not ready for test.
|
FIR14-00531
| INSP-Sprinkler Rough-in/Hydro | 6/30/2015 | 6/30/2015 | 6/30/2015 4:15:31 PM | P | PASS |
|
|
Hydrotests of floors 2 and 4 wet pipe systems - 200 psi @ 2hrs - PASSED NOTE: Floor 3 had a leak, and floor 5 is not ready for test.
|
FIR14-00430
| INSP-Sprinkler Rough-in/Hydro | 6/30/2015 | 6/30/2015 | 6/30/2015 4:13:32 PM | P | PASS |
|
|
Hydrotests of two (2) dry pipe systems protecting the grade level parking garage. - 200 psi @ 2 hrs - PASSED
|
FIR14-00430
| INSP-Sprinkler Rough-in/Hydro | 6/29/2015 | 6/30/2015 | 6/30/2015 2:54:55 PM | P | CANC |
|
|
Wrong permit called in for this area. See FIR14-00531 for inspections completed today (6/30).
|
FIR14-00531
| INSP-Sprinkler Rough-in | 6/30/2015 | 6/30/2015 | 6/30/2015 2:51:54 PM | P | PART |
|
|
RTC inspection for under pool deck area - off of fitness room system. OK to cover.
|
FIR13-00725
| INSP-Sprinkler Rough-in | 6/30/2015 | 6/30/2015 | 6/30/2015 1:12:55 PM | P | PASS |
|
|
Hydrotest of first fllor dry pipe system protecting A/G parking garage (around Helix). 200 psi @ 2 hours - PASSED
|
FIR13-00725
| INSP-Sprinkler Rough-in | 6/29/2015 | 6/30/2015 | 6/30/2015 1:09:40 PM | A | CANC |
|
|
Wrong permit number for this inspection. See FIR13-00167 for FS U/G hydrotest inspection this date.
|
FIR13-00167
| INSP-Sprinkler Rough-in/Hydro | 6/30/2015 | 6/30/2015 | 6/30/2015 12:17:15 PM | P | PASS |
|
|
Hydrostatic test of FS U/G supply line from 11th St. city connection to main BFP in basement riser room. PASSED
|
FIR13-00178
| FIR-Aging Inspection | 6/30/2015 | 6/30/2015 | 6/30/2015 12:10:45 PM | | CANC |
|
|
Wrong permit called in for this inspection. See FIR 13-00167 for hydrotest of U/G supply line (11th street connection).
|
FIR15-00096
| INSP-Sprinkler Rough-in | 6/29/2015 | 6/30/2015 | 6/30/2015 10:31:45 AM | A | CANC |
|
|
|