FIR11-00296
| FIR-Aging Inspection | 6/4/2013 | 6/4/2013 | 6/5/2013 9:02:19 AM | | NR |
|
|
I spoke to Rick Phone #: ###-#### with Public Works, and he said different options are being investigated for a solution.
|
FIR13-00171
| INSP-Sprinkler Rough-in/Hydro | 6/4/2013 | 6/4/2013 | 6/4/2013 3:19:57 PM | P | PASS |
|
|
Hydro test and sprinkler rough-in passed. As-builts have been provided.
|
BLD12-03289
| FIRE-Final Inspection | 6/4/2013 | 6/4/2013 | 6/4/2013 3:14:53 PM | P | FAIL |
|
|
Provide floor plan that matches, provide single action hardware on the main exit and if the dead bolt is to remain it shall be keyed on the inside, and provide annual inspection for the fire extinguisher.
|
BLD13-00303
| FIRE-Final Inspection | 6/3/2013 | 6/4/2013 | 6/4/2013 2:49:54 PM | P | FAIL |
|
|
Mike did not have the approved plans/notes on site for this permit so I performed an inspection for BLD13-01062 which was not scheduled.
|
FIR12-00286
| INSP-Final Inspection | 5/30/2013 | 6/4/2013 | 6/4/2013 11:34:26 AM | A | FAIL |
|
|
Need to perform the forward flush and perform a depth, flush and hydro inspection on the underground supply as per discussion. Also need to verify the flow switch function/interconnection with the facp.
|
FIR13-00132
| INSP-Final Inspection | 6/4/2013 | 6/4/2013 | 6/4/2013 11:06:18 AM | P | PASS |
|
|
Permit finaled
|
BLD11-00519
| FIRE-Final Inspection | 5/30/2013 | 6/4/2013 | 6/4/2013 10:39:45 AM | A | FAIL |
|
|
The project related fire sprinkler permit needs to be addressed which includes all aspects of the underground supply piping to the fire sprinkler system. Also no city approved plans/notes were on site for an inspection.
|
FIR13-00020
| INSP-Sprinkler Rough-in | 6/3/2013 | 6/4/2013 | 6/4/2013 10:05:27 AM | A | PASS |
|
|
Tenting inspection is passed at 2030. Sprinkler piping can be covered.
|