Inspections for the day of: Thursday, June 4, 2015.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorRex Boyles
TitleELE-INSPECTOR
Phone #685-9023
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE13-01291 Electrical Rough-In6/2/20156/4/20156/4/2015 1:11:03 PMPPASS
Contact Brandon Robinson for east side of level 1 site lighting underground. Phone #: ###-#### Inspection requested via web by Tom Betty r/i ok marketplace area A and H underground conduits under foam.
ELE15-01423 Electrical Rough-In6/4/20156/4/20156/4/2015 12:33:18 PMPPART
Elmer Phone #: ###-#### r/i ok ceiling,south,east and west walls in back half of garage
ELE15-01637 Final6/4/20156/4/20156/4/2015 12:00:00 PMPCANC
Inspection requested via web by Shawna Gates needed p/s
ELE15-01637 Permanent Service6/4/20156/4/20156/4/2015 11:58:59 AMPPASS
Inspection requested via web by Shawna Gates p/s o/h rec ok will look for water bond at final
ELE15-01654 Final6/3/20156/4/20156/4/2015 11:31:05 AMANH
Phone #: ###-#### Inspection requested via web by steve ragan no answer at door, called Asher and waited 10 minutes. He called but still no access
ELE14-03333 Electrical Rough-In6/3/20156/4/20156/4/2015 10:27:32 AMAPASS
Contact: Jeremy Thornock Phone #: ###-#### Inspection requested via web by Deb Gooden r/i ok remainder of parking garage ceiling ok to cover.
ELE14-01819 Final6/3/20156/4/20156/4/2015 10:26:22 AMAPASS
Contact: Jeremy Thornock Phone #: ###-#### Inspection requested via web by Deb Gooden finalok spoke with Jeremy and this permit was pulled to start project. ELE14-03333 is the main project permit still in progress.
ELE14-03517 Conference6/3/20156/4/20156/4/2015 9:02:35 AMADONE
Consultation please Phone #: ###-#### Inspection requested via web by Celinda Winters discuss terminations in generator ATS and r/i of small section of wall ok
ELE15-01617 Electrical Rough-In6/3/20156/4/20156/4/2015 8:28:11 AMAPASS
Phone #: ###-#### Inspection requested via web by Kerri Hamilton continue primarys to xformer pad ok
ELE15-02131 Electrical Rough-In6/4/20156/4/20156/4/2015 12:00:00 AMAPASS
Shaft inspection 3rd floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok vent. shafts in rms. 308,310,316,333,331 and 325