FIR06-00118
| FIR-Aging Inspection | 6/5/2006 | 6/5/2006 | 6/6/2006 11:27:15 AM | | NR |
|
|
Dave Maxwell said he would follow up on status of job.
|
FIR05-00536
| INSP-Sprinkler Rough-in | 6/5/2006 | 6/5/2006 | 6/6/2006 11:20:19 AM | P | CANC |
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
|
FIR05-00827
| INSP-Sprinkler Rough-in | 6/5/2006 | 6/5/2006 | 6/5/2006 3:46:57 PM | P | PASS |
|
|
All remaining piping is ok to cover
|
FIR06-00247
| INSP-Final Inspection | 6/2/2006 | 6/5/2006 | 6/5/2006 3:45:19 PM | P | PASS |
|
|
Permit finaled
|
MIS06-00133
| FIR-Final | 6/5/2006 | 6/5/2006 | 6/5/2006 2:26:42 PM | P | PART |
|
|
A temporary occupancy was given until a fire extinguisher is provided, remove thumbturn from the north exit and provide indicator, provide approved hardware (lever is ok) on the south exit door, remove or repair the exit sign
|
MIS06-00132
| FIR-Final | 6/5/2006 | 6/5/2006 | 6/5/2006 2:26:08 PM | P | PART |
|
|
A temporary occupancy was given until a fire extinguisher is provided, remove thumbturn from the north exit and provide indicator, provide approved hardware (lever is ok) on the south exit door.
|
FIR06-00200
| INSP-Sprinkler Rough-in/Hydro | 6/5/2006 | 6/5/2006 | 6/5/2006 1:42:41 PM | P | FAIL |
|
|
See city approved plans for locations where the upright sprinkler heads are being blocked by steel beams. Additional heads will be required. This inspection was for the overhead shell system piping only and did not include the riser or tenant improvement spaces.
|
BLD05-03024
| FIRE-Final Inspection | 6/2/2006 | 6/5/2006 | 6/5/2006 12:09:04 PM | A | CANC |
|
|
inspection was ment for structural inspector
|
BLD05-00631
| FIRE-Final Inspection | 6/2/2006 | 6/5/2006 | 6/5/2006 12:07:26 PM | A | PASS |
|
|
life safety passed
|
BLD05-03414
| FIRE-Final Inspection | 6/2/2006 | 6/5/2006 | 6/5/2006 10:21:26 AM | A | PASS |
|
|
Life safety finaled
|
FIR06-00044
| INSP-Final Inspection | 6/2/2006 | 6/5/2006 | 6/5/2006 10:13:48 AM | A | FAIL |
|
|
The wrong heads have been installed in the racks, VK100 instead of VK550, provide one additional EQ brace for the main and provide additional heads for the head box.
|