Inspections for the day of: Tuesday, June 5, 2012.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD12-01006 FIRE-Final Inspection6/5/20126/5/20126/5/2012 3:50:43 PMPCANC
unit 208 - -Ken Phone #: ###-#### - Inspection canceled per phone conversation with Jim Sly. Project is not ready for inspection. Inspection will be scheduled for next monday.
FIR12-00223 INSP-Sprinkler Rough-in/Hydro6/4/20126/5/20126/5/2012 3:31:54 PMPPASS
The overhead hydro test and rough-in of the north canopy dry system passed. The earth quake bracing on the main has not been installed yet.
FIR12-00279 INSP-Final Inspection6/4/20126/5/20126/5/2012 2:32:28 PMAPASS
Permit finaled
BLD12-00860 FIRE-Final Inspection6/5/20126/5/20126/5/2012 1:41:48 PMPPASS
Life safety passed. Per phone converstion with the fire alarm plan reviewer the single audio/visual device located in the lobby was previously approved under the 1997 UFC and is ok to remain.
FIR12-00223 INSP-Sprinkler Rough-in6/5/20126/5/20126/5/2012 1:39:51 PMPPASS
This entry is for an inspection called in under FIR12-00175 on 5/17/2012.

The overhead hydro test passed. The sprinkler piping in the Sanctuary/Fellowship areas is ok to cover.
BLD12-00460 FIRE-Final Inspection6/4/20126/5/20126/5/2012 12:55:58 PMAPASS
life safety passed
FIR11-00662 FIR-Aging Inspection6/5/20126/5/20126/5/2012 9:47:00 AM NR
Work is in progress
BLD12-00868 FIRE-Final Inspection6/4/20126/5/20126/5/2012 9:27:00 AMAFAIL
Repair or remove the exit sign, mount the fire extinguisher and provide for inspection of the fire sprinkler work.
FIR12-00256 INSP-Final Inspection6/5/20126/5/20126/5/2012 9:25:07 AMPFAIL
Owner scheduled life safety final. No city approved plans for fire sprinkler work on site for inspection of this permit.