Inspections for the day of: Friday, June 5, 2015.
Number of inspections: 20
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMike Jordan
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD15-00128 BLD-Foundation6/4/20156/5/20156/5/2015 3:40:30 PMPDEFR
CMU 1:00PM pour; Tony Phone #: ###-####
BLD15-00485 BLD-Framing/Rough-in6/4/20156/5/20156/5/2015 3:31:47 PMPNR
Steve Phone #: ###-####
BLD15-01747 BLD-Framing/Rough-in6/5/20156/5/20156/5/2015 3:17:45 PMPPASS
Bill-call for access Phone #: ###-####
BLD15-01235 BLD-Framing/Rough-in6/4/20156/5/20156/5/2015 2:59:39 PMPPART
Lance Phone #: ###-####. ok pending elec. rough in inspection.
BLD14-03379 BLD-Wall Bracing6/5/20156/5/20156/5/2015 2:18:10 PMPPASS
Drywall shear connections Phone #: ###-#### Inspection requested via web by Brian Stark
BLD13-03318 BLD-Conference6/4/20156/5/20156/5/2015 2:05:14 PMPDONE
Need to review items from previous inspection. 10 minutes max, Thanks
Phone #: ###-#### Inspection requested via web by Scott Zierler
BLD13-03308 BLD-Final6/5/20156/5/20156/5/2015 1:48:28 PMPNR
Bill Phone #: ###-####. Needs fire/life/safety final.
BLD15-00884 BLD-Final6/5/20156/5/20156/5/2015 1:46:00 PMPPASS
call James prior to going out Phone #: ###-####
BLD15-00884 DOC - Permit Finaled6/5/20156/5/20156/5/2015 1:43:55 PMPPASS
BLD15-01037 BLD-Footing6/4/20156/5/20156/5/2015 11:27:44 AMACANC
Dane Phone #: ###-####
BLD15-01037 BLD-Footing6/4/20156/5/20156/5/2015 11:26:41 AMANR
Dane Phone #: ###-####
BLD15-00841 BLD-Energy code compliance6/4/20156/5/20156/5/2015 11:25:33 AMAPASS
And reframing. // Colby Phone #: ###-####
BLD15-00841 BLD-Framing/Rough-in6/5/20156/5/20156/5/2015 11:25:09 AMAPASS
And reframing. // Colby Phone #: ###-####
BLD15-01437 BLD-Wall Bracing6/4/20156/5/20156/5/2015 11:00:34 AMAFAIL
shear//Zemima Phone #: ###-####. Provide approved fix for modified trusses, A2 and gable end truss bearing at incorrect locations, provide additional brackets for treat 2x4 bearing studs above and below. Correction notice issued.
BLD15-01101 BLD-Energy code compliance6/2/20156/5/20156/5/2015 10:33:04 AMAPASS
Bill Phone #: ###-####
BLD14-02369 BLD-Foundation6/4/20156/5/20156/5/2015 10:23:41 AMAPASS
Manual Phone #: ###-####
BLD15-00884 BLD-Final6/4/20156/5/20156/5/2015 10:12:43 AMAFAIL
James Phone #: ###-####. Remove the occupancy light sensor in the electrical room and provide a light switch as indicated on the approved plans.
BLD15-00788 BLD-Ceiling Grid Inspection6/4/20156/5/20156/5/2015 9:54:54 AMAPART
Phone #: ###-#### Inspection requested via web by Darius Saxton. Ok pend. mech.
BLD15-00383 BLD-Framing/Rough-in6/2/20156/5/20156/5/2015 9:29:05 AMAPASS
Rich Phone #: ###-####. Reviewed RFI and reinspected SW exterior facade wall. Ok to insulate. Also inspected reinstallation of existing insulation at parapet. Work in progress on west parapet.
BLD15-00152 BLD-Final6/4/20156/5/20156/5/2015 9:05:14 AMAFAIL
Dan Phone #: ###-####. Provide the required energy cert. and post. Provide the blower door test result or the 3rd party airseal inspection report and post. 20 min. door to residence from garage? Correction notice was posted.