FIR20-00122
| INSP-Final Inspection | 6/4/2020 | 6/5/2020 | 6/5/2020 2:29:33 PM | P | PASS |
|
|
Final fire sprinkler inspection is complete. Irrigation shutdown during flow switch activation observed.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
FIR20-00108
| INSP-Final Inspection | 6/4/2020 | 6/5/2020 | 6/5/2020 2:28:17 PM | P | PASS |
|
|
Final fire sprinkler inspection is complete. Irrigation shutdown during flow switch activation observed.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
FIR20-00109
| INSP-Final Inspection | 6/4/2020 | 6/5/2020 | 6/5/2020 2:27:24 PM | P | PASS |
|
|
Final fire sprinkler inspection is complete. Irrigation shutdown during flow switch activation observed.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
FIR20-00098
| INSP-Final Inspection | 6/4/2020 | 6/5/2020 | 6/5/2020 2:27:04 PM | P | PASS |
|
|
Final fire sprinkler inspection is complete. Irrigation shutdown during flow switch activation observed.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
FIR20-00127
| INSP-Final Inspection | 6/4/2020 | 6/5/2020 | 6/5/2020 2:26:42 PM | P | PASS |
|
|
Final fire sprinkler inspection is complete. Irrigation shutdown during flow switch activation observed.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
FIR20-00122
| INSP-Sprinkler Rough-in/Hydro | 6/4/2020 | 6/5/2020 | 6/5/2020 2:25:07 PM | P | DONE |
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed at city pressure, no pressure loss observed at riser provided gauge.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
FIR20-00108
| INSP-Sprinkler Rough-in/Hydro | 6/4/2020 | 6/5/2020 | 6/5/2020 2:24:40 PM | P | DONE |
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed at city pressure, no pressure loss observed at riser provided gauge.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
FIR20-00109
| INSP-Sprinkler Rough-in/Hydro | 6/4/2020 | 6/5/2020 | 6/5/2020 2:24:08 PM | P | DONE |
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed at city pressure, no pressure loss observed at riser provided gauge.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
FIR20-00098
| INSP-Sprinkler Rough-in/Hydro | 6/4/2020 | 6/5/2020 | 6/5/2020 2:23:42 PM | P | DONE |
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed at city pressure, no pressure loss observed at riser provided gauge.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
FIR20-00127
| INSP-Sprinkler Rough-in/Hydro | 6/4/2020 | 6/5/2020 | 6/5/2020 2:23:41 PM | P | DONE |
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed at city pressure, no pressure loss observed at riser provided gauge.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
FIR20-00341
| INSP-Sprinkler Rough-in | 6/4/2020 | 6/5/2020 | 6/5/2020 9:18:57 AM | A | PASS |
|
|
Rough to cover inspection for area of work is complete, approved for cover.
Contact Tanner Loomis ###-#### 30 Min prior to RTC insp start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
FIR20-00374
| INSP-Sprinkler Rough-in | 6/4/2020 | 6/5/2020 | 6/5/2020 8:25:49 AM | A | PASS |
|
|
Rough to cover inspection for area of work is complete, approved for cover.
Please call Nate with time frame. Phone #: ###-#### Inspection requested via web by Jeff Packham
|
BLD19-04590
| FIRE-Final Inspection | 6/4/2020 | 6/5/2020 | 6/5/2020 8:01:17 AM | A | PASS |
|
|
Previously noted items have been corrected, door hardware was being changed at time of inspection, will be completed before BLD final. No fire sprinklers, no fire alarms, firee xtinguishers are placed with current inspection tags. Final life fire safety inspection for area of work is complete, signature provided on permit sign off card.
call for access- August *screened* Phone #: ###-####
|