Inspections for the day of: Tuesday, June 6, 2000.
Number of inspections: 13
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorGerry Varner
TitlePLM-INSPECTOR
Phone #447-7209
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
PLM00-01897 Sprinkler (Final)6/5/20006/6/20006/6/2000 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/05/2000 at 10:39:10. Contact: ###-####. Sprkl. final 6/7/00 4:37:17 PM
PLM00-01795 Sprinkler (Final)6/5/20006/6/20006/6/2000 12:00:00 AMAPASS
reinspection sprinkler tiera ###-#### Sprkl. final 6/7/00 4:37:03 PM
PLM00-01907 Final6/5/20006/6/20006/6/2000 12:00:00 AMAPASS
Eric ###-#### R/I and final ok 6/7/00 4:36:57 PM
PLM00-01797 Water and/or Sewer6/5/20006/6/20006/6/2000 12:00:00 AMAPASS
Greg Barney ###-#### Water service final 6/7/00 4:36:45 PM
PLM00-01468 Final6/5/20006/6/20006/6/2000 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/05/2000 at 15:06:43. Contact: ###-####. Final ok 6/7/00 4:36:50 PM
PLM00-01339 Roof Drains6/5/20006/6/20006/6/2000 12:00:00 AMAPART
Scheduled by a contractor via Hello! on 06/05/2000 at 15:07:47. Contact: ###-####. Roof drains ok 6/7/00 4:37:11 PM
PLM00-01908 Plumbing Rough-in6/5/20006/6/20006/6/2000 12:00:00 AMAFAIL
Scheduled by a contractor via Hello! on 06/05/2000 at 15:55:57. Contact: ###-####. Relocate WH 6/7/00 4:36:36 PM
PLM00-01723 Plumbing Rough-in6/5/20006/6/20006/6/2000 12:00:00 AMPPART
Scheduled by a contractor via Hello! on 06/05/2000 at 16:48:07. Contact: ###-####. Partial R/I opk 6/7/00 4:37:30 PM
PLM00-01886 Plumbing Rough-in6/5/20006/6/20006/6/2000 12:00:00 AMPPART
Scheduled by a contractor via Hello! on 06/05/2000 at 16:51:53. Contact: ###-####. Partial R/I ok 6/7/00 4:37:24 PM
PLM00-01808 Roof Drains6/6/20006/6/20006/6/2000 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 06/06/2000 at 08:03:32. Contact: ###-####. GW ok 6/7/00 4:37:37 PM
PLM00-01915 Plumbing Rough-in6/6/20006/6/20006/6/2000 12:00:00 AMPPART
###-#### Partial R/I ok 6/7/00 4:38:09 PM
PLM00-01581 Final6/6/20006/6/20006/6/2000 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 06/06/2000 at 09:33:06. Contact: ###-####. Final ok 6/7/00 4:38:04 PM
PLM99-04210 Plumbing Rough-in6/6/20006/6/20006/6/2000 12:00:00 AMPFAIL
shelly ###-#### Install traps and select- inlarge plumbing vent 6/7/00 4:37:57 PM