Inspections for the day of: Thursday, June 6, 2002.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorDixie Fellows
TitleMEC-COM/RES INSPECTOR
Phone #794-6208
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MEC02-01513 Final6/5/20026/6/20026/6/2002 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/05/2002 at 15:01:28. Contact: ###-####.
MEC02-01470 Rough-in6/5/20026/6/20026/6/2002 12:00:00 AMAFAIL
Scheduled by a contractor via Hello! on 06/05/2002 at 15:19:26. Contact: ###-####. posted corrections 6/6/2002 12:43:04 PM
MEC02-01470 Pressure Test6/5/20026/6/20026/6/2002 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/05/2002 at 15:19:43. Contact: ###-####.
MEC02-01116 Final6/5/20026/6/20026/6/2002 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/05/2002 at 16:14:14. Contact: ###-####.
MEC02-01263 Rough-in6/5/20026/6/20026/6/2002 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/05/2002 at 16:25:17. Contact: ###-####. main line into bldg 20# test ok 6/6/2002 9:28:30 AM
MEC02-01494 Pressure Test6/6/20026/6/20026/6/2002 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/06/2002 at 06:58:15. Contact: ###-####.
MEC02-01444 Rough-in6/6/20026/6/20026/6/2002 12:00:00 AMPFAIL
###-#### bob posted corrections talked with cont 6/6/2002 2:11:33 PM
MEC02-01455 Pressure Test6/6/20026/6/20026/6/2002 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 06/06/2002 at 09:48:56. Contact: ###-####.
MEC02-01494 Final6/6/20026/6/20026/6/2002 12:00:00 AMPCANC
Scheduled by a contractor via Hello! on 06/06/2002 at 10:32:20. Contact: .
MEC02-01511 Rough-in6/6/20026/6/20026/6/2002 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 06/06/2002 at 10:52:11. Contact: ###-####.
MEC02-01474 Rough-in6/6/20026/6/20026/6/2002 12:00:00 AMPPASS
butler heating
MEC01-02624 Pressure Test6/4/20026/6/20026/6/2002 12:00:00 AMPNR
ROBERT ###-####