BLD08-00344
| FIRE-Final Inspection | 6/6/2008 | 6/6/2008 | 6/6/2008 2:23:11 PM | P | PASS |
|
|
Kil- fire life saftey Phone #: ###-####
|
BLD07-03193
| FIRE-Final Inspection | 6/6/2008 | 6/6/2008 | 6/6/2008 2:22:52 PM | P | PART |
|
|
Still need site work complete at both entrances-paving is not finished-need to comply with fire department access requirements-see fire code review notes for specific details.
|
FIR07-00606
| INSP-Sprinkler Rough-in | 6/5/2008 | 6/6/2008 | 6/6/2008 2:15:50 PM | A | FAIL |
|
|
Overhead rough-in inspection for the auditoruim area failed due to overspaced upright heads, missing coverage at the SW stair landing, provide flexible couplings at the 4' main where lacking correct seismic clearance at the block walls east and west sides, noted changes in pipe routing of the 4" main not indicated on plans at the intersection of the catwalk and cross main, the north half of the pendent heads at cloud ceilings are not yet complete, noted site made EQ braces consisting of unistrut and bent 3/8" all-thread rod attatched to truss webs are not approved or listed for this use-provide materials and components installed in such a way to meet appropriate guidelines per NFPA 13.
|
FIR08-00334
| INSP-Final Inspection | 6/5/2008 | 6/6/2008 | 6/6/2008 1:45:19 PM | A | PASS |
|
|
Fire alarm testing passed, one notification appliance at the mens restroom properly secured while on site, permit finaled.
|
BLD08-00011
| FIRE-Final Inspection | 6/6/2008 | 6/6/2008 | 6/6/2008 12:31:00 PM | P | DEFR |
|
|
vince - fire life safety Phone #: ###-####
|
FIR08-00361
| INSP-Sprinkler Rough-in | 6/5/2008 | 6/6/2008 | 6/6/2008 11:37:44 AM | A | FAIL |
|
|
The second floor middle and left end units have been sheetrocked prior to overhead rough-in inspection, completed satisfactory flow testing and OH inspection for the right side unit 1st and 2nd floors, noted missing flow switch and outside bell at all units, discussed shoutoff valve signage and head box placement.
|
BLD08-00925
| FIRE-Alarm Testing | 6/5/2008 | 6/6/2008 | 6/6/2008 10:05:45 AM | A | FAIL |
|
|
Lacking the required fire alarm permit for interconnection of the existing building fire alarm system to the new hood suppression equipment per IFC and NFPA 72-see also attatched fire code review notes for details. Noted alarm work has been completed without a permit and will incur double fees.
|
FIR07-00879
| INSP-Sprinkler Rough-in/Hydro | 6/4/2008 | 6/6/2008 | 6/6/2008 9:37:25 AM | P | NR |
|
|
Not ready for inspection per contractor due to lacking water supply.
|
FIR08-00376
| INSP-Sprinkler Rough-in | 6/5/2008 | 6/6/2008 | 6/6/2008 9:23:36 AM | A | PART |
|
|
Approved for cover at the drop ceiling areas within the tenant remodel.
|
FIR07-00879
| INSP-Supply line flush | 6/4/2008 | 6/6/2008 | 6/6/2008 9:15:34 AM | P | CANC |
|
|
This is an ug flush. I have a hydro scheduled for earlier this day also. Brian D is the contact. Thanks Phone #: ###-#### Internet Inspection Request from: Stan Beus
|
BLD08-00127
| FIRE-Final Inspection | 6/6/2008 | 6/6/2008 | 6/6/2008 9:11:57 AM | P | CANC |
|
|
Scheduled by a contractor via Hello! on 6/6/2008 at 6:53:19 AM. Contact: ###-####.
|
FIR08-00155
| FIR-Aging Inspection | 6/6/2008 | 6/6/2008 | 6/6/2008 8:06:45 AM | | DONE |
|
|
Pending site inspection request.
|