Inspections for the day of: Wednesday, June 6, 2012.
Number of inspections: 28
Percentage of inspections complete: 79 %
Percentage of inspections not complete: 21 %
Contact Information
InspectorMike Jordan
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC11-00778 Aging Inspection5/31/20125/31/2012   
ESC12-00164 Site Preparation6/1/20126/1/2012   
ESC12-00525 Site Preparation6/1/20126/1/2012   
ESC12-00530 Site Preparation6/4/20126/4/2012   
ESC11-00785 Aging Inspection6/5/20126/5/2012   
ESC11-00852 Site Final6/6/20126/6/20126/6/2012 4:16:20 PMPDONE
ESC11-00852 DOC - Permit Finaled6/6/20126/6/20126/6/2012 4:16:11 PMPPASS
BLD11-02867 BLD-Final6/5/20126/6/20126/6/2012 4:16:00 PMPPASS
John Phone #: ###-####
BLD11-02867 DOC - Permit Finaled6/6/20126/6/20126/6/2012 4:15:52 PMPPASS
MIS12-00147 BLD-Conference6/6/20126/6/20126/6/2012 3:34:48 PMPCANC
BLD12-01213 BLD-Framing/Rough-in6/6/20126/6/20126/6/2012 3:32:12 PMPPASS
call 1/2 hr prior//Ken Phone #: ###-####
ESC12-00298 Random Inspection6/6/20126/6/20126/6/2012 2:45:57 PMPPASS
BLD12-00689 BLD-Energy code compliance6/6/20126/6/20126/6/2012 2:45:41 PMPPASS
Johnny Phone #: ###-####
BLD12-00513 BLD-Final6/6/20126/6/20126/6/2012 1:42:23 PMPFAIL
Peter Phone #: ###-####. Post the required energy cert and provide the third party energy seal check list or the blower door test results and post. A correction notice was posted.
ESC12-00214 Site Final6/6/20126/6/20126/6/2012 1:41:01 PMPDONE
ESC12-00214 DOC - Permit Finaled6/6/20126/6/20126/6/2012 1:40:53 PMPPASS
MIS12-00147 BLD-Conference6/5/20126/6/20126/6/2012 1:40:33 PMAFAIL
A remodel was completed with no permits. A correction notice was issued to submit plans to plan review for review and approval, obtain all required inspections for cert. of completion. Noted to have plans submitted by 6-15-12. A five day notice will be issued the following monday if plans have not been submitted.
BLD12-01436 BLD-Footing6/5/20126/6/20126/6/2012 11:24:11 AMAPASS
James Phone #: ###-####
BLD12-00383 BLD-Framing/Rough-in6/5/20126/6/20126/6/2012 11:10:39 AMADEFR
Tom Phone #: ###-####. Welding and bolting. Reviewed special inspection reports. ok.
ESC12-00164 General Inspection6/6/20126/6/20126/6/2012 11:09:44 AMAPASS
BLD12-01206 BLD-Wall Bracing6/5/20126/6/20126/6/2012 10:53:20 AMAPASS
Gary Phone #: ###-####
ESC12-00495 Random Inspection6/6/20126/6/20126/6/2012 10:53:04 AMAPASS
BLD12-00248 BLD-Other6/5/20126/6/20126/6/2012 10:23:38 AMAPASS
Rick early if possible Phone #: ###-####. Ceiling grid ok.
ESC12-00114 General Inspection6/6/20126/6/20126/6/2012 9:56:35 AMAPASS
BLD12-00282 BLD-Framing/Rough-in6/5/20126/6/20126/6/2012 9:56:10 AMAPASS
garrett Phone #: ###-####. Canopy framing ok. Also recieved RFI for new header deatil at new opening. All work done per approved plans and RFI.
ESC12-00410 General Inspection6/6/20126/6/20126/6/2012 9:23:29 AMAPASS
BLD12-00947 BLD-Framing/Rough-in6/5/20126/6/20126/6/2012 9:23:16 AMAPASS
Phone #: ###-#### >> Inspection requested via web by Kelly Stover. ok to insulate.
ESC12-00485 General Inspection6/6/20126/6/2012