BLD11-02367
| FIRE-Final Inspection | 5/29/2013 | 5/30/2013 | | A | |
|
|
Contact on site, or Dave at ###-####
|
FIR13-00133
| INSP-Sprinkler Rough-in | 6/4/2013 | 6/6/2013 | 6/6/2013 10:28:10 PM | A | PART |
|
|
Shell system rough-in completed for the 16th and 17th floors. Noted five areas on the 17th floor and two areas on the 16th floor in need of revision- field changes to piping layout in the remote calc area on the 16th floor, floorplan change on the 17th floor SW corner, missing and obstructed heads at some locations, overspaced coverage at the mens restroom 17th floor. Coverage below ductwork incomplete at this time.
|
FIR13-00057
| INSP-Sprinkler Rough-in | 6/6/2013 | 6/6/2013 | 6/6/2013 10:16:33 PM | A | PART |
|
|
Fire sprinkler work at the sheetrock soffits in meeting room 301 approved for cover. Plans clouded and dated.
|
BLD13-01264
| FIRE-Final Inspection | 6/5/2013 | 6/6/2013 | 6/6/2013 10:12:32 PM | A | PASS |
|
|
C/N items finished. Fire life safety finaled.
|
BLD13-00522
| FIRE-Final Inspection | 6/5/2013 | 6/6/2013 | 6/6/2013 10:50:03 AM | A | PASS |
|
|
Fire life safety inspection passed.
|