FIR13-00205
| INSP-Final Inspection | 6/5/2013 | 6/6/2013 | 6/6/2013 3:44:26 PM | P | PASS |
|
|
permit finaled
|
BLD12-03126
| FIRE-Conference | 6/6/2013 | 6/6/2013 | 6/6/2013 3:31:57 PM | P | DONE |
|
|
Life safety will be ok to sign off when the project related fire sprinkler, fire alarm permits are finaled and when the emergency lighting as marked on the city approved plans have been provided/repaired.
|
FIR13-00171
| INSP-Final Inspection | 6/4/2013 | 6/6/2013 | 6/6/2013 3:20:11 PM | P | PASS |
|
|
permit finaled
|
FIR13-00144
| INSP-Final Inspection | 6/6/2013 | 6/6/2013 | 6/6/2013 3:00:31 PM | P | PASS |
|
|
permit finaled
|
FIR13-00163
| INSP-Sprinkler Rough-in | 6/5/2013 | 6/6/2013 | 6/6/2013 2:02:21 PM | A | PASS |
|
|
See the city approved plans for locations marked ok where the sprinkler piping can be covered.
|
BLD13-01232
| FIRE-Final Inspection | 6/5/2013 | 6/6/2013 | 6/6/2013 1:35:14 PM | A | FAIL |
|
|
Provide "fire dept ingress" doors as per the approved plans with the exit sign/emergency lights. Provide revised rack layout if not all of the racking is going to be installed.
|
BLD12-03081
| FIRE-Final Inspection | 6/6/2013 | 6/6/2013 | 6/6/2013 1:00:45 PM | P | PASS |
|
|
life safety passed
|
BLD13-00670
| FIRE-Final Inspection | 6/5/2013 | 6/6/2013 | 6/6/2013 11:51:52 AM | A | PASS |
|
|
life safety passed
|
BLD11-03019
| FIRE-Final Inspection | 6/4/2013 | 6/6/2013 | 6/6/2013 11:12:53 AM | P | FAIL |
|
|
Fire Life and safety can ve passed when the project related fire alarm and fire sprinkler permits have been addressed.
|
BLD13-01396
| FIRE-Final Inspection | 6/5/2013 | 6/6/2013 | 6/6/2013 10:58:17 AM | A | PASS |
|
|
Life safety passed
|
FIR13-00058
| INSP-Final Inspection | 5/31/2013 | 6/6/2013 | 6/6/2013 10:54:40 AM | A | FAIL |
|
|
Provide adjustment for the PIV and test
|
FIR12-00427
| INSP-Final Inspection | 6/5/2013 | 6/6/2013 | 6/6/2013 10:52:22 AM | A | FAIL |
|
|
Forward flush verification is needed and the PIV tamper switch needs to be adjusted.
|
FIR13-00081
| INSP-Final Inspection | 6/5/2013 | 6/6/2013 | 6/6/2013 10:38:43 AM | A | FAIL |
|
|
Need all of the notification circuits tested and updated as-builts provided prior to a final sign off.
|
BLD12-03081
| FIRE-Final Inspection | 6/6/2013 | 6/6/2013 | 6/6/2013 10:34:27 AM | P | FAIL |
|
|
Post the building address and provide remove the three dead bolts.
|