Inspections for the day of: Thursday, June 6, 2013.
Number of inspections: 14
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR13-00205 INSP-Final Inspection6/5/20136/6/20136/6/2013 3:44:26 PMPPASS
permit finaled
BLD12-03126 FIRE-Conference6/6/20136/6/20136/6/2013 3:31:57 PMPDONE
Life safety will be ok to sign off when the project related fire sprinkler, fire alarm permits are finaled and when the emergency lighting as marked on the city approved plans have been provided/repaired.
FIR13-00171 INSP-Final Inspection6/4/20136/6/20136/6/2013 3:20:11 PMPPASS
permit finaled
FIR13-00144 INSP-Final Inspection6/6/20136/6/20136/6/2013 3:00:31 PMPPASS
permit finaled
FIR13-00163 INSP-Sprinkler Rough-in6/5/20136/6/20136/6/2013 2:02:21 PMAPASS
See the city approved plans for locations marked ok where the sprinkler piping can be covered.
BLD13-01232 FIRE-Final Inspection6/5/20136/6/20136/6/2013 1:35:14 PMAFAIL
Provide "fire dept ingress" doors as per the approved plans with the exit sign/emergency lights. Provide revised rack layout if not all of the racking is going to be installed.
BLD12-03081 FIRE-Final Inspection6/6/20136/6/20136/6/2013 1:00:45 PMPPASS
life safety passed
BLD13-00670 FIRE-Final Inspection6/5/20136/6/20136/6/2013 11:51:52 AMAPASS
life safety passed
BLD11-03019 FIRE-Final Inspection6/4/20136/6/20136/6/2013 11:12:53 AMPFAIL
Fire Life and safety can ve passed when the project related fire alarm and fire sprinkler permits have been addressed.
BLD13-01396 FIRE-Final Inspection6/5/20136/6/20136/6/2013 10:58:17 AMAPASS
Life safety passed
FIR13-00058 INSP-Final Inspection5/31/20136/6/20136/6/2013 10:54:40 AMAFAIL
Provide adjustment for the PIV and test
FIR12-00427 INSP-Final Inspection6/5/20136/6/20136/6/2013 10:52:22 AMAFAIL
Forward flush verification is needed and the PIV tamper switch needs to be adjusted.
FIR13-00081 INSP-Final Inspection6/5/20136/6/20136/6/2013 10:38:43 AMAFAIL
Need all of the notification circuits tested and updated as-builts provided prior to a final sign off.
BLD12-03081 FIRE-Final Inspection6/6/20136/6/20136/6/2013 10:34:27 AMPFAIL
Post the building address and provide remove the three dead bolts.