BLD18-01246
| FIRE-Final Inspection | 6/4/2019 | 6/6/2019 | 6/6/2019 5:05:08 PM | P | PART |
|
|
Final life fire safety inspection for core and shell substantially complete. Radio test for fire department radio coverage did not pass. A TCO is authorized per conversation with Ron Johnson with Boise Fire contingent on radio coverage issue being resloved, all other items for life fire safety have been inspected and passed.
Phone #: ###-#### Inspection requested via web by Sam Reading
|
FIR18-00967
| INSP-Final Inspection | 6/3/2019 | 6/6/2019 | 6/6/2019 5:02:27 PM | P | PART |
|
|
Final inspection for scope of work has been performed, install is code compliant, permit will remain in issued status until School District AES (FIR18-00344, instructed by Boise Fire to not final any FIR permits associated with addresses that have an open permit for AES) communicator is inspected and passed. After AES is completed then an inspection request will need to be made to final this permit.
Bret Bailey, Dispatcher Phone #: ###-#### Inspection requested via web by John Siewert
|
FIR18-00964
| INSP-Sprinkler Rough-in | 6/4/2019 | 6/6/2019 | 6/6/2019 4:44:49 PM | P | DONE |
|
|
Fire pump commissioning complete.
Fire pump start up test. Lonnie Phone #: ###-#### Inspection requested via web by Lonnie Greenfield
|
BLD19-00483
| FIRE-Final Inspection | 6/5/2019 | 6/6/2019 | 6/6/2019 4:43:01 PM | A | FAIL |
|
|
Fire alarm contractor did not request an inspection, project associated FIR permits need to be finaled before life fire safety can be performed.
To coincide with Alarm test scheduled by Johnson Controls/TYCO. Phone #: ###-#### Inspection requested via web by Ryan Wilhelm
|
FIR19-00303
| INSP-Supply line flush | 6/5/2019 | 6/6/2019 | 6/6/2019 11:03:46 AM | A | DONE |
|
|
Underground main line flush complete.
Schedule with Troy for time to meet with Suez. Troy Phone #: ###-#### Inspection requested via web by Nathan Stenquist
|
FIR19-00217
| INSP-Final Inspection | 6/5/2019 | 6/6/2019 | 6/6/2019 9:56:47 AM | A | CANC |
|
|
Due to inspection timing inspection request will be rescheduled for a later date. This request cancelled per conversation with point of contact.
before 11 // Drew Phone #: ###-####
|
BLD18-03833
| FIRE-Final Inspection | 6/6/2019 | 6/6/2019 | 6/6/2019 9:55:59 AM | A | PASS |
|
|
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are placed with current inspection tags. Final life fire safety inspection for area of work complete.
|
FIR19-00366
| INSP-Final Inspection | 6/5/2019 | 6/6/2019 | 6/6/2019 9:54:55 AM | A | PASS |
|
|
Final fire alarm inspection for scope of work complete.
Call prior to going Phone #: 2089853303 >> Inspection requested via mobile web by Mike Kroll
|
FIR18-00856
| INSP-Final Inspection | 6/5/2019 | 6/6/2019 | 6/6/2019 9:54:05 AM | A | PART |
|
|
Final inspection for scope of work has been performed, install is code compliant, permit will remain in issued status until School District AES (FIR18-00225, instructed by Boise Fire to not final any FIR permits associated with addresses that have an open permit for AES) communicator is inspected and passed. After AES is completed then an inspection request will need to be made to final this permit.Please call Clarence a couple of hours before heading out. No one is on site.
Thank you Phone #: ###-#### Inspection requested via web by Jessia Maxwell
|