FIR05-00259
| INSP-Sprinkler Rough-in | 6/7/2005 | 6/7/2005 | 6/7/2005 4:17:31 PM | P | PASS |
|
|
Tenting in new addition is passed. Storage areas and concealed combustible areas still need addressed
|
FIR05-00217
| INSP-Sprinkler Rough-in/Hydro | 6/7/2005 | 6/7/2005 | 6/7/2005 3:50:55 PM | P | PART |
|
|
The remaining part of the dry system passed. Not all arm overs have been installed and will need inspected. Final head spacing to be checked when t-bar is installed.
|
FIR05-00275
| INSP-Final Inspection | 6/6/2005 | 6/7/2005 | 6/7/2005 3:46:41 PM | A | CANC |
|
|
To be rescheduled.
|
BLD00-03010
| FIRE-Sprinkler Rough-in | 6/6/2005 | 6/7/2005 | 6/7/2005 1:12:29 PM | A | CANC |
|
|
Not ready for inspection. Exit signs/emergency lights not installed. Doors not installed.
|
FIR05-00259
| INSP-Sprinkler Rough-in/Hydro | 6/6/2005 | 6/7/2005 | 6/7/2005 12:21:44 PM | A | PART |
|
|
See city approved plans for locations of deficiencies. Lower system south end not installed yet. Hydro test passed but was only partial test.
|
BLD03-01980
| FIRE-Final Inspection | 6/6/2005 | 6/7/2005 | 6/7/2005 11:02:29 AM | A | PASS |
|
|
Fire life safety finaled
|