Inspections for the day of: Tuesday, June 7, 2016.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR15-00822 INSP-Final Inspection6/6/20166/7/20166/7/2016 2:46:07 PMAPART
I stopped at the project site three times today to verify static pressure on the underground supply line. At 7:00am the pressure was at 61psi, at 9:00am the pressure was at 71psi and at 1:00pm the pressure was at 74 psi. I contacted the project superintendant and the fire sprinkler contractor and let them know that I could not sign off until directed by my supervisor.

Mike is the contact. Thanks. Phone #: ###-#### Inspection requested via web by Stan Beus
FIR16-00361 INSP-Sprinkler Rough-in/Hydro6/7/20166/7/20166/7/2016 2:28:35 PMPPASS
Piping above hardlids is ok to cover.
FIR16-00152 INSP-Sprinkler Rough-in6/6/20166/7/20166/7/2016 1:22:23 PMACANC
Paul Phone #: ###-####
BLD16-01990 FIRE-Final Inspection6/6/20166/7/20166/7/2016 11:34:32 AMAPASS
life safety passed
BLD16-01492 FIRE-Final Inspection6/6/20166/7/20166/7/2016 8:42:24 AMAFAIL
Jim and I discussed the need for drawings and small documents that were not on site. I accessed the fire review notes and went over many of the listed items.
FIR16-00349 INSP-Final Inspection6/6/20166/7/20166/7/2016 8:41:23 AMAPASS
Permit finaled