FIR04-00748
| INSP-Final Inspection | 6/8/2005 | 6/8/2005 | 6/8/2005 4:12:35 PM | P | PASS |
|
|
permit finaled
|
BLD05-00736
| FIRE-Final Inspection | 6/6/2005 | 6/8/2005 | 6/8/2005 3:51:35 PM | P | CANC |
|
|
Scheduled by a contractor via Hello! on 6/6/2005 at 7:47:43 AM. Contact: ###-####.
|
FIR05-00275
| INSP-Final Inspection | 6/8/2005 | 6/8/2005 | 6/8/2005 3:19:50 PM | P | PASS |
|
|
Fire sprinkler finaled
|
BLD04-02121
| FIRE-Final Inspection | 6/7/2005 | 6/8/2005 | 6/8/2005 2:04:47 PM | A | PASS |
|
|
Fire life safety already finaled
|
FIR05-00205
| INSP-Final Inspection | 6/7/2005 | 6/8/2005 | 6/8/2005 12:04:36 PM | A | FAIL |
|
|
Relocate and test the door holder, verify correct heights for all a/v's and repair/test fire dampers.
|
FIR04-00593
| INSP-Supply line flush | 6/3/2005 | 6/8/2005 | 6/8/2005 10:14:41 AM | A | PASS |
|
|
Forward flow test for the backflow preventer passed, head wrench, sign on bell and map have been supplied. Need backflow certification, canopies and tags on riser.
|