Inspections for the day of: Tuesday, June 8, 2010.
Number of inspections: 18
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR06-00015 INSP-Conference6/4/20106/8/20106/8/2010 3:51:18 PMADONE
Per James he is still trying to get with Mike. Follow up inspection has been set up in two weeks.
FIR06-00062 INSP-Conference6/4/20106/8/20106/8/2010 3:50:53 PMADONE
Per James he is still trying to get with Mike. Follow up inspection has been set up in two weeks.
FIR05-00021 INSP-Conference6/4/20106/8/20106/8/2010 3:50:27 PMADONE
Per James he is still trying to get with Mike. Follow up inspection has been set up in two weeks.
FIR10-00039 INSP-Conference6/4/20106/8/20106/8/2010 3:50:02 PMADONE
Per James he is still trying to get with Mike. Follow up inspection has been set up in two weeks.
FIR10-00036 INSP-Conference6/4/20106/8/20106/8/2010 3:49:38 PMADONE
Per James he is still trying to get with Mike. Follow up inspection has been set up in two weeks.
BLD10-01049 FIRE-Final Inspection6/8/20106/8/20106/8/2010 3:45:19 PMPFAIL
Provide single action hardware for office door 112, provide a tagged and mounted fire extinguisher for the basement area and provide a current inspection tag for the fire extinguisher on the main level.
BLD09-00323 FIRE-Conference6/7/20106/8/20106/8/2010 3:40:38 PMADONE
I went over live safety requirements which included a knox box, manual locks on the interior doors, fire extinguishers and exit signs/emergency lights.
FIR09-00728 INSP-Final Inspection6/7/20106/8/20106/8/2010 2:39:36 PMPPASS
Permit finaled.
FIR10-00147 INSP-Sprinkler Rough-in6/7/20106/8/20106/8/2010 1:07:59 PMACANC
The fire sprinkler plans have been resubmitted and are in the review status. I let rick know I would do the inspection when the new plans had been re-issued.
BLD10-00814 FIRE-Final Inspection6/7/20106/8/20106/8/2010 11:48:21 AMAFAIL
Repair the insulation at the roof deck since it is obstructing the upright sprinkler protection, repair the emergency light in the warehouse area and provide a fire extinguisher in the mezzanine.
BLD10-00691 FIRE-Final Inspection6/7/20106/8/20106/8/2010 10:43:27 AMAFAIL
Provide signage on the door into the UPS room and on the outside and inside of the electrical equipment/batterys as per the approved plans/notes. Also smoke detection is required in the UPS room as per the approved plans/notes.
FIR10-00234 INSP-Final Inspection6/4/20106/8/20106/8/2010 10:41:54 AMAPASS
Permit finaled
BLD10-00196 FIRE-Final Inspection6/7/20106/8/20106/8/2010 10:19:20 AMAPASS
Life safety passed.
BLD10-00198 FIRE-Final Inspection6/7/20106/8/20106/8/2010 10:17:18 AMAPASS
Life safety passed.
FIR10-00133 INSP-Final Inspection6/7/20106/8/20106/8/2010 10:16:11 AMAPASS
Permit finaled
FIR10-00226 INSP-Final Inspection6/1/20106/8/20106/8/2010 10:03:05 AMAPASS
Permit finaled. Netcon was 5.
FIR10-00227 INSP-Final Inspection6/1/20106/8/20106/8/2010 10:02:24 AMAPASS
Permit finaled. Netcon was 5.
FIR07-01003 INSP-Sprinkler Rough-in6/7/20106/8/20106/8/2010 10:01:30 AMAPASS
The sprinkler piping is ok to cover.