BLD12-00956
| FIRE-Sprinkler Rough-in | 6/8/2012 | 6/8/2012 | 6/8/2012 3:58:01 PM | P | PASS |
|
|
sprinkler piping is ok to cover
|
FIR11-00662
| INSP-Alarm Testing | 6/6/2012 | 6/8/2012 | 6/8/2012 3:53:09 PM | P | DONE |
|
|
Todays inspection verified the facp and nac panels. Also tested were the fire sprinkler interconnections Devices tested ok but several have different addresses and locations. The nac wireing includes 18 guage from the panel to the sync modules then back to the nac can then continues to the nac circuits with 12 guage wire. I will need to speak to plan review if this will be allow with EOL verification. The fire alarm system currently has multiple trouble and ground faults being displayed. Also no sprinkler head has been installed in the elevator equipment rooms. The heat detector can be deleted but the smoke will remain for alternate recall.
|
FIR12-00161
| INSP-Final Inspection | 6/7/2012 | 6/8/2012 | 6/8/2012 3:47:50 PM | P | FAIL |
|
|
Todays inspection was for the riser room tamper and flow switches as well as the tamper and flow switches for the west stair well floor control assemblies. The standpipe tamper switches were tested as well except for the east tamper which has not been connected to the fire alarm sytem yet. Forward flush passed. Flow switch delay was adjusted while I waited for most flow switches. A sticker is needed for the outside alarm bell.
|
FIR11-00563
| INSP-Final Inspection | 6/8/2012 | 6/8/2012 | 6/8/2012 3:43:08 PM | A | PASS |
|
|
Permit finaled
|
FIR11-00517
| INSP-Final Inspection | 6/8/2012 | 6/8/2012 | 6/8/2012 3:42:25 PM | A | PASS |
|
|
Permit finaled
|
BLD12-01266
| FIRE-Final Inspection | 6/4/2012 | 6/8/2012 | 6/8/2012 3:29:15 PM | P | FAIL |
|
|
Resubmit plans showing the second floor storage room and the balcony in the sanctuary, provide fire extinguishers for the second floor storage area and the balcony if considered occupyable. post the occupant load signs. A fire alarm system is not required per phone discussion with scott and tim.
|
FIR12-00258
| INSP-Sprinkler Rough-in | 6/7/2012 | 6/8/2012 | 6/8/2012 10:34:54 AM | A | PASS |
|
|
The additional work is passed. Sprinkler piping can be covered.
|