Inspections for the day of: Friday, June 9, 2000.
Number of inspections: 28
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Sly
TitleBLD-COM/RES INSPECTOR
Phone #794-9465
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD99-03112 BLD-Framing/Rough-in6/7/20006/9/20006/9/2000 12:00:00 AMAPART
kirt ###-#### Shear ok 6/13/00 11:54:17 AM
BLD00-00831 BLD-Framing/Rough-in6/8/20006/9/20006/9/2000 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/08/2000 at 06:42:59. Contact: . energy code pass 6/13/00 11:53:35 AM
BLD00-01123 BLD-Framing/Rough-in6/8/20006/9/20006/9/2000 12:00:00 AMAPART
Scheduled by a contractor via Hello! on 06/08/2000 at 09:46:24. Contact: ###-####. Ceiling grid ok 6/13/00 11:53:05 AM
BLD00-00847 BLD-Framing/Rough-in6/8/20006/9/20006/9/2000 12:00:00 AMAPASS
elliott ###-####
BLD00-00479 BLD-Framing/Rough-in6/8/20006/9/20006/9/2000 12:00:00 AMAPART
###-#### Ok to cover- prev. corr. completed except. c/N need spec. insp/approval on welding S.W. column 2nd floor. 6/13/00 11:52:57 AM
BLD99-03068 BLD-Final6/8/20006/9/20006/9/2000 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/08/2000 at 15:28:32. Contact: . C/C #19536 6/13/00 11:53:13 AM
BLD00-00964 BLD-Framing/Rough-in6/9/20006/9/20006/9/2000 12:00:00 AMAPART
Scheduled by a contractor via Hello! on 06/09/2000 at 07:18:47. Contact: ###-####. Ok to cover interior walls only...rebar front column ok 6/13/00 11:53:28 AM
BLD00-00338 BLD-Final6/9/20006/9/20006/9/2000 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/09/2000 at 07:27:20. Contact: ###-####. c/c #19534 6/13/00 11:54:25 AM
BLD00-00864 BLD-Framing/Rough-in6/8/20006/9/20006/9/2000 12:00:00 AMAFAIL
harry ###-#### C/N issued on shear insp 6/13/00 11:54:03 AM
BLD00-01159 BLD-Footing6/8/20006/9/20006/9/2000 12:00:00 AMAPART
###-#### Foot appears ok 6/13/00 11:53:41 AM
BLD00-00581 BLD-Final6/8/20006/9/20006/9/2000 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/08/2000 at 16:02:11. Contact: ###-####. c/C #19535 6/13/00 11:54:10 AM
BLD00-00792 BLD-Framing/Rough-in6/8/20006/9/20006/9/2000 12:00:00 AMAPART
pj ###-#### Shear ok 6/13/00 11:53:48 AM
BLD00-00978 BLD-Framing/Rough-in6/9/20006/9/20006/9/2000 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 06/09/2000 at 07:12:46. Contact: ###-####.
BLD99-02085 BLD-Framing/Rough-in6/8/20006/9/20006/9/2000 12:00:00 AMPFAIL
exterior sheet rock on soffit Mike ###-####
BLD00-01141 BLD-Energy code compliance6/6/20006/9/20006/9/2000 12:00:00 AMPPASS
Mike ###-####
BLD00-00641 BLD-Framing/Rough-in6/9/20006/9/20006/9/2000 12:00:00 AMPPASS
last thing today please johnny ###-####
BLD00-01319 BLD-Foundation6/9/20006/9/20006/9/2000 12:00:00 AMPPASS
wall insp re-bar Mark ###-####
BLD00-01468 BLD-Footing6/9/20006/9/20006/9/2000 12:00:00 AMPPART
ray ###-####
BLD00-00867 BLD-Footing6/9/20006/9/20006/9/2000 12:00:00 AMPPART
###-####
BLD00-01252 BLD-Framing/Rough-in6/9/20006/9/20006/9/2000 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 06/09/2000 at 08:34:34. Contact: ###-####.
BLD00-01139 BLD-Footing6/9/20006/9/20006/9/2000 12:00:00 AMPPASS
Peter ###-####
BLD00-01278 BLD-Framing/Rough-in6/9/20006/9/20006/9/2000 12:00:00 AMPPASS
###-#### shear and frame pass
BLD00-01013 BLD-Framing/Rough-in6/9/20006/9/20006/9/2000 12:00:00 AMPPASS
late pm please darby ###-####
BLD00-00242 BLD-Final6/8/20006/9/20006/9/2000 12:00:00 AMPCANC
Scheduled by a contractor via Hello! on 06/08/2000 at 15:29:53. Contact: . Disp set to [CANC] by a contractor via Hello! on 06/09/2000 at 11:27:07.
BLD99-02201 BLD-Footing6/8/20006/9/20006/9/2000 12:00:00 AMPPART
Clay ###-####
BLD00-01311 BLD-Framing/Rough-in6/8/20006/9/20006/9/2000 12:00:00 AMPPASS
mike ###-#### spot check air at energy inspection
BLD00-00079 BLD-Final6/8/20006/9/20006/9/2000 12:00:00 AMPFAIL
Claire, ###-#### - late afternoon c/n need plans verify temp. glass at doors
BLD00-00983 BLD-Framing/Rough-in6/8/20006/9/20006/9/2000 12:00:00 AMPPASS
bill ###-####