PLM00-01754
| Sprinkler (Final) | 6/8/2000 | 6/9/2000 | 6/9/2000 12:00:00 AM | A | PART |
|
|
michelle ###-#### roll clamps on main tie in, unions at dcva, test dcva 6/9/00 10:25:21 AM
|
PLM00-01210
| Sprinkler (Final) | 6/8/2000 | 6/9/2000 | 6/9/2000 12:00:00 AM | A | PART |
|
|
Charles Rishel ###-#### tie in ok needs testing 6/9/00 10:41:38 AM
|
PLM99-03436
| Final | 6/8/2000 | 6/9/2000 | 6/9/2000 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 06/08/2000 at 11:46:36. Contact: ###-####. provide access to fixtures 6/9/00 10:44:03 AM
|
PLM00-01987
| Sprinkler (Final) | 6/8/2000 | 6/9/2000 | 6/9/2000 12:00:00 AM | P | PASS |
|
|
###-####
|
PLM00-01995
| Groundwork | 6/9/2000 | 6/9/2000 | 6/9/2000 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 06/09/2000 at 08:07:17. Contact: ###-####.
|
PLM00-00783
| Final | 6/9/2000 | 6/9/2000 | 6/9/2000 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 06/09/2000 at 09:02:06. Contact: ###-####.
|
PLM00-02000
| Plumbing Rough-in | 6/9/2000 | 6/9/2000 | 6/9/2000 12:00:00 AM | P | PASS |
|
|
kim ###-#### r/iri ok with shielded coupling at tie in 6/9/00 3:52:26 PM
|
PLM00-02008
| Sprinkler (Final) | 6/9/2000 | 6/9/2000 | 6/9/2000 12:00:00 AM | P | PASS |
|
|
Added by Inspector: 330 On 6/9/00 sprinkler final ok
|
PLM00-01716
| Sprinkler (Final) | 6/9/2000 | 6/9/2000 | 6/9/2000 12:00:00 AM | P | PASS |
|
|
Added by Inspector: 330 On 6/9/00 final ok
|