FIR16-00324
| INSP-Final Inspection | 6/8/2016 | 6/9/2016 | 6/9/2016 2:28:36 PM | P | CANC |
|
|
To be rescheduled for tomorrow morning for a hydro.
|
BLD16-02002
| FIRE-Final Inspection | 6/8/2016 | 6/9/2016 | 6/9/2016 1:53:50 PM | A | FAIL |
|
|
Provide sticker at exit door, porvide ADA single action hardware at the exit door, remove the thumbturn deadbolt at the exit door (keyed ok), mount the fire extinguisher. I let the tenant know that the building inspector may require all interior hardware to be ADA
|
FIR16-00131
| INSP-Supply line flush | 6/6/2016 | 6/9/2016 | 6/9/2016 1:15:31 PM | P | PASS |
|
|
Certification fo the two fire pumps passed today. Papaer work to be provided when finalized.
|
FIR15-00891
| INSP-Final Inspection | 6/9/2016 | 6/9/2016 | 6/9/2016 12:17:21 PM | P | PASS |
|
|
permit finaled
|
FIR15-00891
| INSP-Alarm Testing | 6/9/2016 | 6/9/2016 | 6/9/2016 12:16:18 PM | P | PASS |
|
|
Permit finaled
|
FIR16-00324
| INSP-Sprinkler Rough-in/Hydro | 6/8/2016 | 6/9/2016 | 6/9/2016 11:26:52 AM | A | PART |
|
|
General rough-in passed. Earth quake bracing has not been installed yet. Need more supply pipe installed prior to hydro test. Need as-builts showing the four additional heads installed on kick backs on the west end of the system. The combustible concealed spaces/double walls will need to be addressed prior to a cover inspection.
|
FIR16-00105
| INSP-Supply line flush | 6/8/2016 | 6/9/2016 | 6/9/2016 9:35:55 AM | A | PASS |
|
|
Underground supply line flush passed
|
FIR15-00891
| INSP-Alarm Testing | 6/8/2016 | 6/9/2016 | 6/9/2016 7:15:38 AM | A | FAIL |
|
|
South pull station is too low, north pull station is too high and no signals went to the monitoring station
|