PLM98-01195
| INSP - Final | 6/30/1998 | 7/1/1998 | 7/1/1998 12:00:00 AM | A | PASS |
|
|
06/30/98 347 - w/c2 b2b t1 s1 si1 w/b w/h1 347 7/1/8
|
PLM98-01495
| INSP - Final | 6/30/1998 | 7/1/1998 | 7/1/1998 12:00:00 AM | A | PASS |
|
|
06/30/98 347 - w/c1 b1 s1 l/t1 w/b1 final o/k 347 7/1/8
|
PLM98-01923
| INSP - Plumbing Rough-in | 7/1/1998 | 7/1/1998 | 7/1/1998 12:00:00 AM | P | PART |
|
|
07/01/98 347 - partial inspection water only on #7 & #8 o/k 347 7/1 8
|
PLM98-02050
| INSP - Final | 7/1/1998 | 7/1/1998 | 7/1/1998 12:00:00 AM | P | PASS |
|
|
07/01/98 347 - reinspect sprinkler o/k 347 7/1/8
|
PLM98-02051
| INSP - Final | 7/1/1998 | 7/1/1998 | 7/1/1998 12:00:00 AM | P | PASS |
|
|
07/01/98 347 - reinspect sprinkler o/k 347 7/1/8
|
PLM98-02062
| INSP - Final | 7/1/1998 | 7/1/1998 | 7/1/1998 12:00:00 AM | P | PASS |
|
|
07/01/98 347 - sprinkler final o/k 347 7/1/8
|
PLM98-02087
| INSP - Final | 7/1/1998 | 7/1/1998 | 7/1/1998 12:00:00 AM | P | PASS |
|
|
water line and backflow Dave ###-#### o/k 347 7/1/8
|
PLM98-02094
| INSP - Plumbing Rough-in | 7/1/1998 | 7/1/1998 | 7/1/1998 12:00:00 AM | P | PASS |
|
|
07/01/98 347 - roughin o/k 347 7/1/8
|