Inspections for the day of: Monday, July 1, 2002.
Number of inspections: 28
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMike Kinnear
TitleELE-INSPECTOR
Phone #794-1379
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE02-01922 Rough-In Permanent Service6/28/20027/1/20027/1/2002 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/28/2002 at 07:19:09. Contact: ###-####. ok cover ri p/s u/g n ok 7/1/2002 9:00:09 AM
ELE02-01922 Rough-In Permanent Service6/28/20027/1/20027/1/2002 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/28/2002 at 07:19:09. Contact: ###-####. ok cover ri p/s u/g n ok 7/1/2002 9:00:09 AM
ELE02-01044 Final6/28/20027/1/20027/1/2002 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/28/2002 at 11:06:19. Contact: ###-####. ok final survey arc fualt not tripping 7/1/2002 9:34:59 AM
ELE02-01044 Final6/28/20027/1/20027/1/2002 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/28/2002 at 11:06:19. Contact: ###-####. ok final survey arc fualt not tripping 7/1/2002 9:34:59 AM
ELE02-01901 Temporary Service6/28/20027/1/20027/1/2002 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/28/2002 at 13:50:31. Contact: ###-####.t/s u/g n ok 7/1/2002 9:34:18 AM
ELE02-01901 Temporary Service6/28/20027/1/20027/1/2002 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/28/2002 at 13:50:31. Contact: ###-####.t/s u/g n ok 7/1/2002 9:34:18 AM
ELE01-04271 Final6/28/20027/1/20027/1/2002 12:00:00 AMANH
Scheduled by a contractor via Hello! on 06/28/2002 at 14:17:16. Contact: ###-####. called contractor tomeet & show us area of work done 7/1/2002 10:58:15 AM
ELE02-01497 Final6/28/20027/1/20027/1/2002 12:00:00 AMANH
TONY ###-#### no access 7/1/2002 8:59:46 AM
ELE02-01497 Final6/28/20027/1/20027/1/2002 12:00:00 AMAPASS
TONY ###-#### ok final 7/1/2002 9:51:47 AM
ELE02-01971 Temporary Service6/28/20027/1/20027/1/2002 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/28/2002 at 16:58:46. Contact: ###-####. t/s u/g n ok 7/1/2002 8:34:47 AM
ELE02-01971 Temporary Service6/28/20027/1/20027/1/2002 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/28/2002 at 16:58:46. Contact: ###-####. t/s u/g n ok 7/1/2002 8:34:47 AM
ELE02-01963 Electrical Rough-In6/30/20027/1/20027/1/2002 12:00:00 AMAPART
Scheduled by a contractor via Hello! on 06/30/2002 at 05:30:25. Contact: ###-####. conf with contractor 7/1/2002 10:58:37 AM
ELE02-01963 Electrical Rough-In6/30/20027/1/20027/1/2002 12:00:00 AMAPART
Scheduled by a contractor via Hello! on 06/30/2002 at 05:30:25. Contact: ###-####. conf with contractor 7/1/2002 10:27:27 AM
ELE02-01971 Temporary Service6/28/20027/1/20027/1/2002 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/28/2002 at 16:58:46. Contact: ###-####. t/s u/g n ok 7/1/2002 8:34:47 AM
ELE02-01971 Temporary Service6/28/20027/1/20027/1/2002 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/28/2002 at 16:58:46. Contact: ###-####. t/s u/g n ok 7/1/2002 8:34:47 AM
ELE02-01922 Rough-In Permanent Service6/28/20027/1/20027/1/2002 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/28/2002 at 07:19:09. Contact: ###-####. ok cover ri p/s u/g n ok 7/1/2002 9:00:09 AM
ELE02-01971 Temporary Service6/28/20027/1/20027/1/2002 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/28/2002 at 16:58:46. Contact: ###-####. t/s u/g n ok 7/1/2002 8:34:47 AM
ELE02-01901 Temporary Service6/28/20027/1/20027/1/2002 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/28/2002 at 13:50:31. Contact: ###-####.t/s u/g n ok 7/1/2002 9:34:18 AM
ELE02-01497 Final6/28/20027/1/20027/1/2002 12:00:00 AMAPASS
TONY ###-#### ok final 7/1/2002 9:51:47 AM
ELE02-01922 Rough-In Permanent Service6/28/20027/1/20027/1/2002 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/28/2002 at 07:19:09. Contact: ###-####. ok cover ri p/s u/g n ok 7/1/2002 9:00:09 AM
ELE02-01044 Final6/28/20027/1/20027/1/2002 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/28/2002 at 11:06:19. Contact: ###-####. ok final survey arc fualt not tripping 7/1/2002 9:34:59 AM
ELE02-01984 Electrical Rough-In7/1/20027/1/20027/1/2002 12:00:00 AMPPASS
ALAN ###-#### ok cover ri 7/1/2002 1:52:31 PM
ELE02-01979 Electrical Rough-In7/1/20027/1/20027/1/2002 12:00:00 AMPFAIL
BILL ###-#### corrections NEC348.30(A) & 300.4(D) 7/1/2002 2:55:50 PM
ELE02-01651 Electrical Rough-In7/1/20027/1/20027/1/2002 12:00:00 AMPFAIL
ALAN ###-#### fail concrete covered with dirt need to uncover to see concrete 7/1/2002 1:30:48 PM
ELE02-02006 Electrical Rough-In7/1/20027/1/20027/1/2002 12:00:00 AMPPASS
r/i lloyd ###-####--addition to the back ok cover ri 7/1/2002 1:12:48 PM
ELE02-00428 Final7/1/20027/1/20027/1/2002 12:00:00 AMPPASS
jim ###-#### fn ok final 7/1/2002 12:58:47 PM
ELE02-01458 Electrical Rough-In7/1/20027/1/20027/1/2002 12:00:00 AMPPASS
###-#### ok cover underground conduit & in the slab conduit 7/1/2002 3:53:52 PM
ELE01-03080 Final6/28/20027/1/20027/1/2002 12:00:00 AMPPASS
###-#### ok final 7/1/2002 1:01:17 PM