FIR08-00109
| INSP-Final Inspection | 7/1/2008 | 7/1/2008 | 7/2/2008 9:12:52 AM | P | DEFR |
|
|
Scheduled by a contractor via Hello! on 7/1/2008 at 7:55:22 AM. Contact: ###-####.
|
FIR08-00312
| INSP-Final Inspection | 7/1/2008 | 7/1/2008 | 7/1/2008 4:14:08 PM | P | FAIL |
|
|
NFPA 72 forms, letter of completion were not filled out. No testing performed on smoke detectors, contractor did not have canned smoke. sprinkler flow switch and tamper were tested. No other testing completed.KR
|
FIR08-00288
| INSP-Final Inspection | 7/1/2008 | 7/1/2008 | 7/1/2008 4:06:36 PM | P | PASS |
|
|
Fire sprinkler permit finaled.
|
FIR08-00393
| INSP-Final Inspection | 7/1/2008 | 7/1/2008 | 7/1/2008 3:42:23 PM | P | PASS |
|
|
Fire sprinkler final inspection passed, permit finaled.
|
FIR08-00182
| INSP-Sprinkler Rough-in | 6/30/2008 | 7/1/2008 | 7/1/2008 3:32:15 PM | P | PART |
|
|
UG fire supply line flush completed okay
|
BLD08-01113
| FIRE-Final Inspection | 7/1/2008 | 7/1/2008 | 7/1/2008 3:31:09 PM | P | PASS |
|
|
Fire life safety finaled.
|
FIR08-00376
| INSP-Final Inspection | 7/1/2008 | 7/1/2008 | 7/1/2008 3:30:36 PM | P | PASS |
|
|
Fire sprinkler permit finaled, one missing escutcheon installed while on site.
|
BLD08-01112
| FIRE-Alarm Testing | 7/1/2008 | 7/1/2008 | 7/1/2008 2:04:09 PM | P | DONE |
|
|
Duplicate inspection request.
|
BLD08-00197
| FIRE-Final Inspection | 6/30/2008 | 7/1/2008 | 7/1/2008 2:02:56 PM | A | FAIL |
|
|
Missing ceiling tile at several locations, need to repair one exit sign, one PFE is overdue annual certification at the server room, need to verify door mag locks drop out on fire alarm and power loss, not all items reviewed at this time, discussed subsequent permits for future remodel work.
|
BLD07-02689
| FIRE-Final Inspection | 6/30/2008 | 7/1/2008 | 7/1/2008 1:58:44 PM | A | FAIL |
|
|
Noted overspaced fire sprinkler heads, missing ceiling tile, one non-functional exit sign, locking hardware at several office slider doors is not approved, discussed general fire life safety requirements.
|
FIR08-00268
| INSP-Final Inspection | 6/27/2008 | 7/1/2008 | 7/1/2008 11:44:54 AM | A | PASS |
|
|
Fire alarm testing completed.3 Pull stations were to high. Pull stations were lower while I was on site testing sprinkler system.Retest pull stations. KR
|
FIR08-00300
| INSP-Final Inspection | 6/30/2008 | 7/1/2008 | 7/1/2008 11:41:41 AM | A | PASS |
|
|
Fire sprinkler hydro completed also final inspection. KR
|
BLD08-01113
| FIRE-Alarm Testing | 6/30/2008 | 7/1/2008 | 7/1/2008 11:30:22 AM | A | PASS |
|
|
Fire life safety inspection passed, one missing fire sprinkler escutcheon replaced while on site, noted project related fire sprinkler permit needs requested for final as well as correct inspection type called in for the BLD permit as "fire final" to ensure accurate documentation.
|
BLD08-00797
| FIRE-Final Inspection | 7/1/2008 | 7/1/2008 | 7/1/2008 11:25:44 AM | P | FAIL |
|
|
Fire extinguisher mounted to high, top of handle needs to be max 48" also needs cert tag. Address needs to be installed. All locking door handles need to be replaced with compliant handles. Dead bolt on back door needs to be removed. Need to install sign above main exit, door to remain unlocked while occupied.KR
|
FIR07-00902
| INSP-Sprinkler Rough-in | 6/30/2008 | 7/1/2008 | 7/1/2008 11:24:42 AM | A | PART |
|
|
Forward flow of the DCVA backflow preventer completed satisfactory.
|
BLD08-01112
| FIRE-Conference | 6/30/2008 | 7/1/2008 | 7/1/2008 11:23:03 AM | A | FAIL |
|
|
Need to repair two EM lights, exit door hardware at the east side exit is not approved, project related fire sprinkler permit needs to be requested for final, one PFE at the kitchen installed while on site, need to resolve plenum rated data cable issue.
|
FIR08-00210
| INSP-Sprinkler Rough-in/Hydro | 6/27/2008 | 7/1/2008 | 7/1/2008 11:19:36 AM | A | FAIL |
|
|
Overhead hydrostatic test failed due to start pressure below 200 psi. (guage @ 176 psi).
|
BLD07-03288
| FIRE-Final Inspection | 7/1/2008 | 7/1/2008 | 7/1/2008 10:40:03 AM | P | PASS |
|
|
Changes made per last inspection were completed.KR
|