Inspections for the day of: Friday, July 1, 2011.
Number of inspections: 16
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD11-01016 FIRE-Final Inspection7/1/20117/1/20117/1/2011 3:29:59 PMPPASS
life safety passed
BLD11-01089 FIRE-Final Inspection7/1/20117/1/20117/1/2011 3:20:02 PMPFAIL
Provide single action hardware on the restroom and breakroom doors. Replace all painted sprinkler heads as discussed and per NFPA 13 6.2.6.2. Provide for fire alarm notification in the restroom, washroom and breakroom. This work will require permit. Situation was discussed with Ben.
FIR11-00289 INSP-Sprinkler Rough-in6/30/20117/1/20117/1/2011 3:18:08 PMPPART
The first floor piping, east side of wall, piping passed rough-in inspection. Before a cover approval can be given the insulation needs to be repaired. Also three 2" 90's and an elevation change has been installed on this pipe. Provide verification with Boise City plan review to verify that the hydraulic calculations have not been adversly affected. Provide aux drain as discussed.
FIR11-00014 INSP-Final Inspection7/1/20117/1/20117/1/2011 3:15:48 PMPFAIL
The strobe in room 225 failed to function and the elevator, as per previous discussions, needs to be addressed.
FIR11-00159 INSP-Sprinkler Rough-in6/30/20117/1/20117/1/2011 3:14:45 PMAPASS
The first floor Jewelery area (6) heads and the three heads at the north side of the water curtain are ok to cover.
FIR10-00540 INSP-Sprinkler Rough-in6/30/20117/1/20117/1/2011 3:13:39 PMAPASS
See the city approved plans for the second floor areas that are ok to cover.
BLD10-02149 FIRE-Final Inspection7/1/20117/1/20117/1/2011 2:22:48 PMPPASS
life safety passed
FIR11-00277 INSP-Final Inspection6/30/20117/1/20117/1/2011 12:20:48 PMACANC
Shielded wire needs to be installed and the correct transformer. No inspection was performed.
FIR11-00274 INSP-Final Inspection6/30/20117/1/20117/1/2011 12:18:34 PMACANC
Shielded wire needs to be installed and the correct transformer. No inspection was performed.
FIR11-00276 INSP-Final Inspection6/30/20117/1/20117/1/2011 12:18:17 PMACANC
Shielded wire needs to be installed and the correct transformer. No inspection was performed.
FIR11-00275 INSP-Final Inspection6/30/20117/1/20117/1/2011 12:18:01 PMACANC
Shielded wire needs to be installed and the correct transformer. No inspection was performed.
FIR11-00279 INSP-Final Inspection6/30/20117/1/20117/1/2011 12:17:13 PMACANC
Shielded wire needs to be installed and the correct transformer. No inspection was performed.
FIR11-00278 INSP-Final Inspection6/30/20117/1/20117/1/2011 12:16:56 PMACANC
Shielded wire needs to be installed and the correct transformer. No inspection was performed.
BLD10-00620 FIRE-Final Inspection6/30/20117/1/20117/1/2011 12:15:43 PMAPASS
Life safety passed. Tony to verify signage and repaired emergency light.
BLD11-01009 FIRE-Final Inspection6/30/20117/1/20117/1/2011 12:14:36 PMAPASS
life safety passed
BLD11-00300 FIRE-Final Inspection6/30/20117/1/20117/1/2011 7:32:19 AMAPASS
Life safety passed