ELE20-02153
| Permanent Service | 7/1/2020 | 7/1/2020 | 7/1/2020 2:41:28 PM | P | CANC |
|
|
Phone #: ###-#### Inspection requested via web by Troy Cobb Class 6 pole is required by IDP
|
ELE20-01727
| Final | 7/1/2020 | 7/1/2020 | 7/1/2020 1:25:16 PM | P | PASS |
|
|
Contact Darrin Allen. Late afternoon would be best if possible. Phone #: ###-#### Inspection requested via web by Scott Campbell AFC posted. Ok final.
|
ELE20-01727
| Permanent Service | 7/1/2020 | 7/1/2020 | 7/1/2020 1:24:52 PM | P | PASS |
|
|
AFC posted inside door. p/s u/g n ok
|
ELE20-00191
| Final | 6/30/2020 | 7/1/2020 | 7/1/2020 12:29:49 PM | P | NH |
|
|
House is un occupied Phone #: ###-#### Inspection requested via web by Chris Husted No access. Arrived at 1050 all doors were locked. Contacted electrician who contacted homeowner to unlock house, never did. 2nd trip back was at 1230.
|
ELE20-02245
| Electrical Rough-In | 7/1/2020 | 7/1/2020 | 7/1/2020 12:16:04 PM | P | PASS |
|
|
Right next to Alloway Lighting. Call when in route if possible. Phone #: ###-#### Inspection requested via web by Steve McCloy Ok cover E and W walls and 2 baths
|
ELE20-02128
| Final | 7/1/2020 | 7/1/2020 | 7/1/2020 12:05:03 PM | P | PASS |
|
|
David *screened* Phone #: ###-#### Ok final.
|
ELE19-03145
| Final | 7/1/2020 | 7/1/2020 | 7/1/2020 11:48:32 AM | P | PART |
|
|
“Final” 1st floor Phone #: ###-#### Inspection requested via web by Kevin Burke Ok final whole 1st floor
|
ELE19-00185
| Electrical Rough-In | 6/30/2020 | 7/1/2020 | 7/1/2020 11:15:40 AM | A | PASS |
|
|
screened // Lloyd Phone #: ###-#### Ok cover closet in basement.
|
ELE20-02222
| Final | 6/29/2020 | 7/1/2020 | 7/1/2020 11:14:49 AM | A | PASS |
|
|
Please call the Master Electrician Matthew Jones ###-####. Thanks. Phone #: ###-#### Inspection requested via web by Nicholas Buck Ok final. Line side connection, #6, 60a disc.
|
ELE20-01371
| Final | 6/30/2020 | 7/1/2020 | 7/1/2020 10:38:16 AM | A | PASS |
|
|
There will be someone home. If you have any questions please feel free to contact Jason ###-####. Thanks!! Phone #: ###-#### Inspection requested via web by Clayton Morgan Ok final bathroom
|
ELE20-02237
| Electrical Rough-In | 6/30/2020 | 7/1/2020 | 7/1/2020 10:15:30 AM | A | PASS |
|
|
Underground and bonding for swimming pool. Access granted through construction entrance on left side of residence Phone #: ###-#### Inspection requested via web by Lars Johnson Ok cover grd work, 4 corners, 3 lts E side and main bond back to equipt.
|
ELE20-01290
| Electrical Rough-In | 6/30/2020 | 7/1/2020 | 7/1/2020 10:14:23 AM | A | PASS |
|
|
Need inspection for floor heat in master bathroom Phone #: ###-#### Inspection requested via web by Justin Reynolds Ok cover flr heat mstr
|
ELE20-02244
| Temporary Service | 7/1/2020 | 7/1/2020 | 7/1/2020 9:24:58 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Dean Gernaat t/s o/h n ok
|
ELE20-01585
| Electrical Rough-In | 7/1/2020 | 7/1/2020 | 7/1/2020 9:24:40 AM | A | PASS |
|
|
Key is under pot by back door Phone #: ###-#### Inspection requested via web by Dave Brueggemann Inspection cancelled from web by: Dave Brueggemann Ok cover main level. No work done in upstairs
|
ELE20-02230
| Conference | 6/30/2020 | 7/1/2020 | 7/1/2020 5:55:52 AM | A | DONE |
|
|
Need direction on homemade pool.... Phone #: ###-#### Inspection requested via web by Sean Patton During a service inspection I saw a portable pool on the property that was surrounded by secondary and primary power within the 10' horizontal zone. Asked homeowner (Ashley Alexander) via phone call to verbally commit to removing pool upon final of service. She accepted.
|