ELE17-00330
| ELE-Aging Inspection | 7/1/2020 | 7/1/2020 | 7/2/2020 1:58:50 PM | | DONE |
|
|
see final
|
ELE17-00330
| Final | 7/1/2020 | 7/1/2020 | 7/2/2020 1:58:14 PM | P | PASS |
|
|
Business owner has pasted and it is believed the business is to be dissolved. final ok
|
ELE18-02194
| ELE-Aging Inspection | 7/1/2020 | 7/1/2020 | 7/1/2020 1:14:56 PM | | PASS |
|
|
see final
|
ELE18-02194
| Final | 7/1/2020 | 7/1/2020 | 7/1/2020 1:14:38 PM | P | PASS |
|
|
job complete, final ok
|
ELE18-02139
| ELE-Aging Inspection | 7/1/2020 | 7/1/2020 | 7/1/2020 12:48:49 PM | | PASS |
|
|
see final
|
ELE18-02139
| Final | 7/1/2020 | 7/1/2020 | 7/1/2020 12:48:28 PM | P | PASS |
|
|
UL Listed wall sign, final ok
|
ELE19-02700
| Electrical Rough-In | 6/29/2020 | 7/1/2020 | 7/1/2020 10:14:19 AM | A | PASS |
|
|
Contact Brandon Robinson for rough in walls level 2. Phone #: ###-#### Inspection requested via web by Tom Betty Rough-in ok cover walls in pneumatic rm, generator roms as high lighted on print, signed, dated
|
ELE19-04799
| Conference | 6/30/2020 | 7/1/2020 | 7/1/2020 9:36:58 AM | A | PASS |
|
|
Conference to inspect and discuss bonding in structural concrete around pool area Phone #: ###-#### Inspection requested via web by Jason Parke Discussed and visually observed 4 corner pool bonding stingers stubs, bonding conductor ran back to 4th floor pool equipment room. Pool completion awarded to other pool company, separate permit required.
|
ELE19-04799
| Electrical Rough-In | 6/30/2020 | 7/1/2020 | 7/1/2020 9:28:32 AM | A | PASS |
|
|
Elevated concrete deck rough in- area A level 5 Phone #: ###-#### Inspection requested via web by Jason Parke Rough-in ok cover/ pour Level 5 Eastern half of Area A
|
ELE18-02164
| ELE-Aging Inspection | 7/1/2020 | 7/1/2020 | 7/1/2020 8:38:42 AM | | PEND |
|
|
The permit is still open with the City of Boise. Please call 208 ###-#### with progress report or any questions. If your job is complete, please schedule an final inspection online. Thank you!
|
ELE18-02152
| ELE-Aging Inspection | 7/1/2020 | 7/1/2020 | 7/1/2020 8:38:19 AM | | PEND |
|
|
The permit is still open with the City of Boise. Please call 208 ###-#### with progress report or any questions. If your job is complete, please schedule an final inspection online. Thank you!
|