Inspections for the day of: Tuesday, July 10, 2001.
Number of inspections: 14
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAlan Hauser
TitleMEC-COM/RES INSPECTOR
Phone #794-9453
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MEC01-01187 MEC-Aging Inspection7/10/20017/10/20017/10/2001 12:00:00 AM PASS
MEC01-01025 MEC-Aging Inspection7/10/20017/10/20017/10/2001 12:00:00 AM PASS
MEC01-01006 MEC-Aging Inspection7/10/20017/10/20017/10/2001 12:00:00 AM PASS
MEC01-01013 MEC-Aging Inspection7/10/20017/10/20017/10/2001 12:00:00 AM PASS
MEC01-01023 MEC-Aging Inspection7/10/20017/10/20017/10/2001 12:00:00 AM PASS
MEC01-01007 MEC-Aging Inspection7/10/20017/10/20017/10/2001 12:00:00 AM CANC
MEC01-00913 MEC-Aging Inspection7/10/20017/10/20017/10/2001 12:00:00 AM CANC
MEC01-01326 Pressure Test7/9/20017/10/20017/10/2001 12:00:00 AMAFAIL
pressure test failed, and no drawings of piping, engineered drawings required for 2# system, no table in 97 umc 7/10/2001 10:43:13 AM
MEC01-01873 Pressure Test7/9/20017/10/20017/10/2001 12:00:00 AMAPASS
gas piping into new garage for unit heater has been removed, pipe to dryer and unit heater was undersized, ok for just dryer. 7/10/2001 12:16:06 PM
MEC01-01591 Rough-in7/9/20017/10/20017/10/2001 12:00:00 AMAPASS
both towers ok for cover 7/10/2001 11:27:34 AM
MEC01-01996 Rough-in7/10/20017/10/20017/10/2001 12:00:00 AMPPASS
r/i-- ###-#### jerry r/i
MEC01-01996 Pressure Test7/10/20017/10/20017/10/2001 12:00:00 AMPPASS
jerry-- ###-#### pres test
MEC01-01175 Final7/10/20017/10/20017/10/2001 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 07/10/2001 at 09:47:47. Contact: ###-####.
MEC01-01844 Rough-in7/10/20017/10/20017/10/2001 12:00:00 AMPFAIL
dryer vents covered in walls and to many 90 degree elbows used in dryer vent sections that are 5". icbo interpertation allows 28.5' of horizontal with a deduct of 6' for each 90 used. talked to jeff from western 7/10/2001 3:17:34 PM